Neoen Australia’s 157MW Kaban wind farm has officially connected to Queensland’s “SuperGrid,” the state’s grand new name for the beefed up electricity network that will need to accommodate 80% renewables by 2035.

The wind farm – which is said to be at the half-way mark of construction, with 16 of its 28 Vestas V162-5.6MW EnVentus turbines fully installed – was energised on Tuesday.

The project is part of Neoen Australia’s Green Power Hub, which has plans to add a big battery, and will take in a 320km transmission line upgrade of the coastal circuit from Cairns to Townsville.

The Queensland government’s green energy utility, CleanCo, has signed a 15-year offtake deal to purchase 100 per cent of the output from the wind farm.

Deputy Premier Steven Miles on Tuesday marked the project as the first for the Sunshine State’s first renewable energy zone, the Northern Queensland REZ.

“This project is perfectly positioned to capitalise on the world-renowned wind resources of Northern Queensland,” Miles said.

The milestone for the Neoen project comes less than a week after the Palaszczuk government announced ambitious new renewable energy targets, including 70% by 2032 and 80% by 2035.

Queensland Labor’s new plans aim to add 22GW of new wind and solar, 11.5GW of rooftop solar, 9GW of battery storage and 7GW of pumped hydro storage to a renewable energy SuperGrid, most of it over the coming decade.

The state’s minister for energy, renewables and hydrogen Mick de Brenni said on Tuesday that the government’s $700 million investment in the North Queensland transmission network over the next five years aims to keep the new renewables generation flowing.

“This new transmission infrastructure will be delivered by Powerlink and will unlock an additional 500MW of renewables capacity in the region,” de Brenni said at an event for the Kaban wind farm in the Tablelands.

“Projects like this enable the cost-effective connection of multiple renewable energy developments into the network, making it easier to bring more clean energy to enter the system.”

Neoen managing director Louis de Sambucy said the company was proud of Kaban’s role as the cornerstone project of Queensland’s first renewable energy zone.

“I’d like to thank the Queensland government and CleanCo for their vision and support, and Powerlink for their hard work and commitment in delivering the essential transmission infrastructure,” he said.

Queensland Premier Annastacia Palaszczuk says the energisation of Kaban signifies the first injection of clean energy into the new Queensland SuperGrid.

“Once complete early next year, [the wind farm] will generate 460,000MW hours of clean energy a year, enough to power up to 100,000 homes,” the premier said.

The project is also noted for its huge turbines, which from the base of the tower to the highest tip of the blade reach 230 metres into the air.

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Carbon time bomb: Dutton’s nuclear plan will blow up Paris and emissions targets, CCA says

The Climate Change Authority says a nuclear pathway would add an extra 2 billion tonnes…

24 February 2025

Energy consumers pick up the bill as gas industry prioritises export windfalls

The gas market on the east coast has directly contributed to the cost-of-living crisis. It…

24 February 2025

Victoria solar farm shut down after fire in on-site inverters, must mow grass

Safety regulator closes small Victoria solar farm after inverter fire while it investigates cause and…

24 February 2025

Labor targets wind towers, batteries and electrolysers in $500 million local content support

Labor promises $500 million to ensure locally made steel and aluminium are used in wind…

24 February 2025

APA admits slow progress in Pilbara renewables, as gas industry splits over pipelines and imports

APA says Pilbara wind, solar and battery plans depend on customers, but its main focus…

24 February 2025

The Driven Podcast: Where are we at with V2G?

Oliver Hill, from Race to 2030, on the new roadmap for turning electric cars into…

24 February 2025