Solar

Juwi to complete expansion of Australia’s first grid-scale solar farm, replaces RCR

Published by

Construction of a 30MW addition to Western Australia’s 10MW Greenough River solar farm – the first grid-scale solar farm to be built in Australia – is back on track after the appointment of juwi Renewable Energy to complete the suspended Stage 2 Project.

Project developer Bright Energy Investments said it had appointed juwi for the job, following the late 2018 termination of a previous $60 million contract with RCR O’Donnell Griffin, in the wake of the spectacular failure of parent company RCR Tomlinson.

The Greenough River expansion project, which has been on hold for nine months, is now due to be complete early next year.

The collapse of engineering giant RCR Tomlinson – which went into voluntary administration in November 2018 – sent shock-waves through Australia’s large-scale solar development pipeline, as contracts were terminated and workers pulled from jobs.

As Giles Parkinson reported here, workers were pulled off the sites of at least five major solar projects in Queensland, alone, bringing work on those major PV farms to an effective halt.

RCR has since pointed the finger at “unprofitable solar contracts” in the Australian market as central to the cash-flow issues that have brought the multi-billion dollar company undone.

Since terminating the contract with RCR, BEI has been under pressure to find a replacement to get the Greenough River solar expansion finished in time for W.A. utility Synergy to meet its obligations under the federal government’s renewable energy target.

State-owned Synergy – which owns a nearly 20 per cent stake in BEI – must source at least an additional 300MW of green power by 2020 as part of the LRET.

In a statement on Tuesday, BEI general manager Tom Frood said the new contract would get the project back in progress immediately, with a revised scheduled for completion in early 2020.

“The expansion of the Greenough River Solar Farm will be an important contributor to Western Australia’s energy supplies and there has been a lot of hard work to gather the project back together and renegotiate a way forward,” Frood said.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Outgunned: Five fossil fuel lobbyists spent $553,000 on Meta ads in August, the renewables industry just $3,090

Fossil fuel lobbyists are flooding social media with ads, outgunning the minimal effort of the…

1 September 2026

How three hours of free solar power can cost you more | SwitchedOn Australia

Solar Sharer exposes a fundamental problem with our energy system – protecting retailer revenues can…

1 September 2026

“Retailer viability” trumped bill savings in Solar Sharer design, says energy veteran

A policy designed to give households access to abundant free solar power has been nobbled…

1 September 2026

“Doing what we built it to do:” Rinehart-backed lithium mine runs on 80 pct renewables for second year in row

As the party backed by Gina Rinehart burns effigies of renewable energy infrastructure, one of…

1 September 2026

One Nation promises to build new coal plants and sweat old ones in energy policy pitch to state voters

One Nation has promised to extend the life of a coal-fired power plant as part…

31 August 2026

Changing tack on Victoria’s energy transition will throw electricity savings into reverse, experts warn

One Nation and Coalition plans to review or roll back Victoria's energy policies would likely…

31 August 2026