Solar

J-Power recommits to Kidston pumped hydro plan, pending new off-take deal

Published by

Genex Power has struck a new agreement with Japanese utility J-Power that renews its interest in buying ab equity stake in the Kidston Pumped Storage Hydro project, subject to a new off take agreement being sealed.

In June, J-Power had agreed to make a $25 million equity investment in the pumped-hydro project, giving the company up to a 19.99% stake in the Genex company.

However, that agreement was contingent on Genex achieving certain milestones before the end of 2019, but the company revealed at the beginning of November that it had encountered delays, largely due to the decision by EnergyAustralia to renegotiate its off-take deal.

That move by EnergyAustralia put both the J-Power agreement, and financing from the Northern Australia Investment Facility (NAIF) at risk, but after securing an extension to the NAIF backing, Genex said on Friday it has secured the same with J-Power.

“We are delighted that J-Power has shown faith in Genex and our K2-Hydro project with the execution of this MOU and to continue discussions along the lines of those originally announced in June this year,” Genex CEO James Harding said in a statement.

“We will work as quickly as we can to conclude arrangements with J-Power as part of the restructuring of the K2-Hydro transaction with a view to reaching financial close for the project as soon as possible in 2020.

“Along with the decision by the NAIF Board to extend the offer of funding for the K2-Hydro announced last week, we are maintaining the momentum we had previously established into the new year.”

The Kidston pumped-hydro project up to 250MW and eight hours of energy storage capacity, using two disused gold mine pits. The project ran into trouble after Australian utility EnergyAustralia, sought to delay the execution of a previously announced off-take agreement with the project.

The project will be co-located with 270MW of solar generation and 150MW of wind capacity. The first stage of the project, a 50MW solar farm, was completed in late 2018.

This delay has forced Genex to renegotiate contracts with other project partners, including J-Power, as a prior deadline to achieve a financial investment decision before the end of 2019, has been pushed into 2020.

 

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.
Michael Mazengarb

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.

Share
Published by

Recent Posts

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024

Solar Insiders Podcast: A roller coaster year in review – and the keys to a smoother 2025

In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…

20 December 2024

CEFC creates buzz with record investment in poles and wires, as Marinus bill blows out again

CEFC winds up 2024 with record investment in two huge transmission projects, as Marinus reveals…

20 December 2024

How big utilities manipulate the energy market, even with a high share of wind and solar

Regulator says big energy players are manipulating prices to their benefit. It's not illegal, but…

20 December 2024