Intrigue as Webuild buys out cash-strapped Snowy 2.0 contractor partner in fire sale

Published by

Intrigue around Australia’s biggest renewable energy project has deepened after the Italian-based Webuild bought its contracting partner in the delayed and over budget Snowy 2.0 project for a peppercorn sum.

The South-African based Murray and Roberts announced overnight that it had agreed to sell its interest in Australian engineering firm Clough to We Build for a cash consideration of just $500,000, and the cancellation of a $350 million intracompany loan.

Murray and Roberts appears to have had little choice but to sell. It revealed earlier this year that the Snowy 2.0 project was delayed and over-budget – something that Snowy Hydro itself has only admitted this week – and that it had no working capital facility for the project, a situation its own CFO described as “ludicrous.”

In its statement, Murray and Roberts says the sale agreement is directly linked to the “acute” problems around working capital pressures being felt largely by Clough, which also precipitated a major share price fall.

“The Group has been reviewing a number of strategic options to address Clough’s working capital needs, which have become increasingly urgent,” it said.

“Having reviewed all available alternatives and based on the above background, the board of directors of Murray & Roberts concluded that a transaction with Webuild was the preferred course of action.”

Murray and Roberts says the cash position of Clough will be boosted by an interim loan facility of $A30 million by Webuild, presumably to enable it to manage its part of the Snowy 2.0 contract. The loan is still dependent on due diligence.

The sale follows confirmation from Snowy Hydro executives this week that the Snowy 2.0 is running over budget and is heavily delayed, and that it is in negotiations with the contractors over the cost issue.

Federal energy minister Chris Bowen in June announced that the project was running up to 18 months behind schedule, amid reports that it could be up to $2 billion over budget due to delays, logistics problems and supply constraints and costs.

Snowy Hydro this week confirmed that the budget for the Snowy 2.0 project has now blown out to just under $6 billion and is running around 12 months behind schedule.

 

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Labor to give households $150 in energy bill relief

$1.8 billion in rebates would slash household bills by an average of 7.5 per cent…

23 March 2025

Why hydrogen exports are a mirage, but green industry isn’t

Australia’s hydrogen strategy has been a mix of ambition, overreach, and slow reality checks.

23 March 2025

Australia’s only silicon producer wins federal funds to cut emissions, boost solar supply chain

Australia’s only silicon manufacturer has been awarded funding from the Albanese Labor government, to help…

21 March 2025

Energy Insiders Podcast: The tipping point in solar and battery storage

Quinbrook's David Scaysbrook says the falling cost of solar and battery storage represents a tipping…

21 March 2025

Renew Economy announces new editor, expanded team and new features

Renew Economy has appointed a new editor, a COO, expanded its team and added new…

21 March 2025

China solar giant unveils new grid battery product with “advanced” fire mitigation

China solar giant says the new 5MWh unit has been designed to withstand Australia’s “complex…

21 March 2025