Intrigue as Webuild buys out cash-strapped Snowy 2.0 contractor partner in fire sale

Published by

Intrigue around Australia’s biggest renewable energy project has deepened after the Italian-based Webuild bought its contracting partner in the delayed and over budget Snowy 2.0 project for a peppercorn sum.

The South-African based Murray and Roberts announced overnight that it had agreed to sell its interest in Australian engineering firm Clough to We Build for a cash consideration of just $500,000, and the cancellation of a $350 million intracompany loan.

Murray and Roberts appears to have had little choice but to sell. It revealed earlier this year that the Snowy 2.0 project was delayed and over-budget – something that Snowy Hydro itself has only admitted this week – and that it had no working capital facility for the project, a situation its own CFO described as “ludicrous.”

In its statement, Murray and Roberts says the sale agreement is directly linked to the “acute” problems around working capital pressures being felt largely by Clough, which also precipitated a major share price fall.

“The Group has been reviewing a number of strategic options to address Clough’s working capital needs, which have become increasingly urgent,” it said.

“Having reviewed all available alternatives and based on the above background, the board of directors of Murray & Roberts concluded that a transaction with Webuild was the preferred course of action.”

Murray and Roberts says the cash position of Clough will be boosted by an interim loan facility of $A30 million by Webuild, presumably to enable it to manage its part of the Snowy 2.0 contract. The loan is still dependent on due diligence.

The sale follows confirmation from Snowy Hydro executives this week that the Snowy 2.0 is running over budget and is heavily delayed, and that it is in negotiations with the contractors over the cost issue.

Federal energy minister Chris Bowen in June announced that the project was running up to 18 months behind schedule, amid reports that it could be up to $2 billion over budget due to delays, logistics problems and supply constraints and costs.

Snowy Hydro this week confirmed that the budget for the Snowy 2.0 project has now blown out to just under $6 billion and is running around 12 months behind schedule.

 

 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

“This has to change:” Flurry of late orders breaks wind drought and gives global turbine giants hope for 2026

A flurry of late orders has broken the wind investment drought in Australia, with global…

23 December 2025

Modelling spot prices in a post-coal grid, when big batteries will become the price setters

Electricity prices can be kept near today’s levels in a post-coal National Electricity Market, but…

23 December 2025

Traditional Owners accuse huge NT solar and battery project of “worst consultation you can think of”

A legal move to extinguish any native claims over land proposed to host the giant…

23 December 2025

Energy Insiders Podcast: Is the wind drought over?

We discuss some of the major events of the past year - the dominance of…

23 December 2025

SEC steps in to rescue another stalled project, an Australian-first wind farm overlooking coal ruins

SEC to build state's first publicly owned wind farm, that will be the first to…

23 December 2025