Battery

Hybrid solar battery systems replace diesel at four remote gold mines

Published by

West Australian gold producer Westgold has replaced six diesel power stations with four hybrid solar, battery and gas systems that are slashing emissions and saving money.

The company contracted Pacific Energy to install the new systems, which have a combined capacity of 82MW, under a seven-year build, own and operate agreement.

All four mines – Tuckabianna, Bluebird, Fortnum and Big Bell facilities – are located in the Mid-West region of Western Australia, and have a combined capacity of 28MW of solar, 11.5MW/6MWh of battery energy storage, and 42.5MW of high-efficiency gas generation.

It is expected that the four hybrid power systems will displace 38 million litres of diesel each year, cutting carbon emissions by up to 57,000 tonnes annually.

Pacific Energy says its hybrid power systems are based around grid forming battery technology, which is able to integrate renewable energy sources and dynamically stabilise power output, essentially mimicking the characteristics of traditional rotating thermal generators.

The new hybrid systems also come with what Pacific Energy describes as an “emergency hydrocarbons-off functionality” which allows for seamless mining operations using solar and battery storage during system outages or other critical situations.

“We’re approaching our systems design with a future-focused mindset, so they can support the increasing sophistication of renewable energy technologies for years to come, and to ensure we’re delivering the decarbonisation outcomes our clients are looking for,” Pacific Energy CEO Jamie Cullen said.

The hybrid power system deployed at Westgold’s Tuckabianna facility was fully commissioned in August 2023 and has since achieved an average solar penetration of 31% between November 2023 and January 2024, peaking at 36.9% in December.

“Moving towards renewables works for Westgold as a business because it drives costs out,” said Westwood CEO Wayne Bramwell.

“It also works for the environment because it significantly reduces carbon emissions, and it sends a signal about our long-term view of building a sustainable business.”

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024