One of the biggest solar and battery storage projects in NSW, located sotuh-east of Dunedoo in the state’s central west – has been given the all-clear by the state’s Independent Planning Commission, although it still needs a green tick from the federal government.

The Birriwa solar farm, being developed by Acen Australia, will comprise a 600 megawatt (MW) solar farm and a 600 MW, 1,200 MWh battery energy storage system. Last week it joined the queue for approval from the federal government under the EPBC Act.

The project was approved earlier this year by the state’s planning department, but because it attracted more than 80 written objections from neighbours – and others who lived more than 100 kms away – it was automatically referred to the IPC.

The objections began with the local Warrumbungle share council, but its concerns about housing construction works was addressed by Acen’s decision to build a camp at the site. Other objections were based on land use, and visual amenity, and the use of surround roads.

The Birriwa project is being built on mostly cleared land currently used for grazing and some cropping, and Acen says grazing activities will continue once the project is complete, as it has done at the New England solar farm, which is the biggest in the country.

The IPC – which conducted a tour of the site, hosted hearings and received 65 written submissions from the community, granted consent to the project, subject to conditions including road restrictions, the preparation of soil and water management plans, and vegetation for visual screening.

Acen, which is also building the 420 MW Stubbo solar project near Mudgee to the south, is one of the biggest renewable and storage developers in the country.

It plans to add a battery to that Stubbo project and is also considering adding battery back-up at its Naragamba, Deeargee and Axedale solar projects.

Last month it added another solar-battery project into the NSW planning pipeline, in this case a 100 megawatt (MW) solar facility and an 80 MW battery to be built near Cooma at the gateway to the Snowy Mountains. It is also seeking to develop the contested Robbins Island Jim Plains wind projects in Tasmania.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Fortescue faces new scrap over fence line for its massive Bonney Downs wind project

The owners of a competing renewable energy hub have had a minor court win in…

13 January 2026

Solar overtakes lignite to keep Germany’s renewable electricity share stable at 55.9 pct in 2025

A boom in solar PV saw output overtake that of lignite power stations and help…

13 January 2026

Queensland LNP flags “call-ins” for two giant battery storage projects, in latest attack on renewable transition

Queensland flags "call ins" for two giant battery projects in the heart of its coal…

13 January 2026

New England locals force huge battery project proposal to go before independent panel

Locals who say they overwhelmed by three neighbouring big battery projects force one gigawatt proposal…

13 January 2026

Grid Connections 2026: Who’s going where and doing what in Australia’s green energy transition

New bosses at Endeavour Energy, Equis Australia, and Janus Electric, a consultant who will not…

13 January 2026

State government allows all five turbines to be built in small wind project

Developer of small wind project in Victoria gets approval for five turbines from state government,…

12 January 2026