Huge 374 tonne machine travels 900km to join NSW renewable super highway

Published by

The latest piece of enormous kit to build out Australia’s transmission infrastructure upgrades required a 128 wheel trailer built in France and a 900km journey to move it from Port Adelaide to Buronga in NSW.

Normally, that trip is just under 400km.

But this piece of kit weighs 374 tonnes and needed a more circuitous route that avoided roads with lighter weight limits and bridges.

It’s the country’s first 330 kV Phase Shifting Transformer (PST), which controls the flow of active power on transmission networks.

Image: Transgrid. Convoy passing through Broken Hill
Image: Transgrid. Convoy passing through Broken Hill

It’s the first of five, with the remaining four to arrive between December this year and January 2024, along with two synchronous condensers and four shunt reactors to make one of the biggest substations in the southern hemisphere, says owner Transgrid.

The Buronga substation will be the main hub connecting Wagga Wagga in NSW to Robertstown in South Australia, with a connection to Red Cliffs in Victoria, on the new 700km EnergyConnect transmission line. 

The $1.8 billion piece of infrastructure saw the first towers erected in March, also at Buronga. It is expected to unlock a swathe of exports from wind and solar projects that are currently curtailed in the solar triangle around Mildura and therefore remove the need for more power from gas and coal generators.

The project is slated for first power from mid to late 2024.

The PST itself was made by Hyosung in South Korea, and took six weeks to ship to Australia. 

The delivery crew, run by Deugro Projects, had permission for road closures in two states over just three days to get the convoy from Port Adelaide up to Broken Hill then down to Buronga via Scotia, travelling at an average 45-50kph.

Image: Transgrid. Convoy driving between Broken Hill and Scotia
Image: Transgrid. Convoy driving between Broken Hill and Scotia

The convoy included a camera operator and a drone pilot to monitor the complex operation.

“This was one of our longest road-trips, and we used drones and other cameras to follow the massive transformer the entire way from Port Adelaide to Buronga,” said Floodlight Content producer Holly Howard.

At Buronga a skid system was used to lift the transformer into position on a concrete pad. The next stage will be to align the interconnection chambers that connect the two transformer tanks together.

Image: Transgrid. Delivery of the transformer at Buronga
Image: Transgrid. Delivery of the transformer at Buronga

Last month, some 1700 cubic metres of concrete was poured for the foundations of the two synchronous condensers.

Once the new 16 hectare substation is completed, it will be the equivalent of a 20-football field expansion to the existing site, Transgrid says.

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Rachel Williamson

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Share
Published by

Recent Posts

Network data blackouts: Why community-led energy projects are so difficult to deliver in Australia

An eight-year struggle to build a community battery has led to a simple proposal: show…

3 August 2026

“A very real risk of breaking:” Councils demand solar recycling as they face avalanche of panels into landfills

Councils fear the consequences of millions of tonnes of solar panels expected in next decade…

3 August 2026

Long in solar, short on storage: Zen Energy faces liquidation as administrators blame high risk strategy

Administrators to renewable energy company Zen Energy point to high risk strategy for company failure,…

3 August 2026

Renewables and electrification help build farm resilience amidst the fuel and fertiliser crisis

The best renewable energy projects won't be the ones that replace farming. They'll be the…

3 August 2026

A battery with every wind turbine | Energy Insiders

Goldwind’s John Titchen explains why and how all new wind turbines could come with their…

3 August 2026

A new oil refinery commissioned in the mid-2030s is just burning money that makes emissions

Isn’t there something better that we should be doing than ensuring we have full tanks…

3 August 2026