Renewables

Huge, 100 tonne turbine tower parts begin arriving at the only wind farm under construction in NSW

Published by

The first batch of turbine parts for the only wind project currently under construction in New South Wales has been delivered to the site of the Uungula wind project, located on Wiradjuri Country 14km east of Wellington in the state’s central West.

Developer Squadron Energy, the renewables outfit owned by Andrew Forrest, said on Thursday that the delivery of almost 900 oversize overmass (OSOM) components started making their way to the site from the Port of Newcastle this week, at a scheduled rate of 26 deliveries a week.

Squadron general manager Mark Hunt says the start of deliveries marks a key construction milestone for the project, and a change in activity on site as teams gear up to start installing the 69 turbines which will make up the 414 megawatt (MW) wind farm.

The deliveries have started with the turbine tower segments and nacelles, some of them weighing up to almost 100 tonnes.

“We’ve been busy completing the turbine foundations on site, with more than 55 now finished, but this is where the work soon starts to become more visual with cranes standing up tower sections ahead of installation,” Hunt said.

Hunt says each turbine is made up of 13 components that will each make the 400 km journey to Wellington from Newcastle via the Golden Highway. Once they reach the site, 750 tonne cranes will be used to lift the turbine pieces into place.

“As we move into the installation phase, a lot the civil work like access roads has finished, so we’ll see a changeover in workforce rather than an increase.

“Our main focus right now is the delivery of turbine tower segments, which range in length from 10 to 36 metres, and nacelles, which sit on top of the tower encasing the gearbox, generator, and brake system.

“We’ll start to move blades, which are the most challenging components due to their length, in the coming months,” Hunt says.

“We thank the community and motorists for their patience while these deliveries take place, we’ve worked hard to ensure the timing of deliveries minimises impacts to the local community.”

Squadron says it has worked closely with principal contractor GE Vernova, transport operator ARES, local councils and relevant agencies to plan deliveries safely and minimise impacts on local communities and road users along the transport route.

Current deliveries from the Port of Newcastle are travelling via the Golden Highway, Saxa Road, continuing via the Mitchell Highway/Goolma Road intersection and Twelve Mile Road to the project site. They are being transported under approved traffic management arrangements.

“Since August last year, we’ve worked closely with Squadron Energy across vessel discharge, laydown, storage and load-out to prepare these oversized components for transport to site at Uungula,” says Port of Newcastle CEO Craig Carmody.

“This milestone demonstrates Port of Newcastle’s capability as Australia’s premiere port for the management of all complex, heavy-lift project cargo and coordination of its safe and efficient movement through the supply chain.”

If you would like to join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

State’s stand-alone solar fail: The energy transition should deliver more than a new landlord

Western Power's stand-alone power system program is not an energy transition solution. It is a…

10 July 2026

Energy Insiders Podcast: Electric truck network starts to take shape

Electric trucks are suddenly big news in Australia. We catch up with NewVolt's Anthony Headlam…

10 July 2026

Watchdog warns spike in home battery complaints could damage consumer trust

Home batteries are flying off shelves and the consumer watchdog wants stronger protection to maintain…

10 July 2026

Offshore wind developers pray for bipartisan support ahead of key state election

Victoria's offshore wind developers are much more optimistic than they were a year ago, but…

10 July 2026

State utility bets on Australian-first compressed CO2 “energy dome,” with up to 12 hours of storage

Victoria's Latrobe Valley will soon host a ground-breaking long-duration energy storage facility capable of continuously…

10 July 2026

“It’s nuts:” Wind developer forced to truck giant transformer thousands of kilometres after port refusal

Renewable developer says the refusal of its closest port to handle a giant transformer has…

10 July 2026