How much has Australia spent on CCS, and what has been achieved?

Published by

Quora.

About 200,000 tons of CO2 has been captured and sequestered in CCA project for power generation at a cost of over $A1 billion since 1998 in various schemes. The cost per tonne sequestered was about $4,300 AUD.

That’s a ratio of one to 38,000 of the CO2 sequestered vs the roughly 9 billion tons of CO2 emitted by Australia since CCS technologies started being investigated. It’s a ratio of about one to 2,300 of the 549 million tons of CO2 emitted by Australia last year alone.

Here are the various carbon capture, distribution and sequestration efforts made in Australia since 1998. Exactly two sequestered some CO2.

About $700 million of this was funded by the Australian government and $300 million by the industry itself, so the coal industry isn’t even paying its own portion of this failure. Australia continues to put lipstick on the pig of CCS with its Coal21 Fund, a tiny pittance of research dollars annually intended to provide air cover for the emissions of the coal industry.

Michael Barnard is a regularly published low-carbon innovation analyst. Source: Quora. Reproduced with permission.

Michael Barnard is a climate futurist, company director, advisor, and author. He publishes regularly in multiple outlets on innovation, business, technology and policy.

Michael Barnard

Michael Barnard is a climate futurist, company director, advisor, and author. He publishes regularly in multiple outlets on innovation, business, technology and policy.

Recent Posts

Advocates unhappy as government seeks oversight of home solar, battery and EVs, rather than regulator

Consumer energy advocates unhappy the federal government will hand technical oversight to its own department…

10 September 2026

Regulator wins fraud conviction against solar installer as Bowen bats off battery rebate rorting claims

Regulator says "enforcement action will be taken where it is warranted," as it secures a…

10 September 2026

Labor dials back gas reservation scheme, denies the move is a policy back-down

The government has tweaked a plan to ease energy prices, with gas producers to only…

10 September 2026

Spanish giant withdraws 2,000 MWh battery project after being “called in” by LNP planning minister

Spanish energy giant withdraws a massive battery project after being "called in" by planning minister,…

10 September 2026

Data centres told to pack their bags for the regions after house full sign goes up in Sydney

Australia's biggest transmission company has effectively put the "house full" sign up for data centres…

10 September 2026

All 200,172 panels in place, as one of Australia’s first solar-battery hybrids hits construction milestone

One of Australia’s first solar and battery hybrid projects has completed the installation of all…

10 September 2026