How long does it take to build a nuclear reactor? We ask France

Published by

A short answer to this question might be, it depends who you ask. Ask Opposition leader Peter Dutton, for instance, and he will tell you a federal Coalition government under his leadership could have a nuclear power plant up and running in Australia within a decade.

Ask the highly experienced French state-owned nuclear power giant EDF, which manages 56 reactors in the world’s most nuclear dependent country, and you would get rather a different answer.

Bloomberg reports that EDF this week got regulatory approval to start up its newest nuclear reactor, the 1.6GW Flamanville plant in France’s north west – a milestone that is 12 years behind schedule and more than four times over budget, thanks to a range of construction problems including concrete weakness and faulty pipe welds.

The green light allows EDF to load the fuel in the reactor, proceed with trials, then begin operations, the Autorite de Surete Nucleaire said in a statement on Tuesday. Further approvals will be needed upon reaching key milestones during the trial phase, the regulator said.

According to other reports, EDF said last month it hoped to connect the Flamanville pressurised reactor to the national grid by the European summer and reach full power by the end of the year.

But it will not be smooth sailing from there. A faulty vessel cover still needs replacing at the plant, with reports suggesting this has been pushed out to 2026, when the plant would be shut down for up to a year.

Meanwhile, EDF in March raised its cost estimate for the construction of six new nuclear reactors to €67.4 billion ($A102.5 billion), Reuters has reported, up from the company’s first estimated their cost of €51.7 billion.

So, how long does it take to build a nuclear reactor?

Kobad Bhavnagri, Bloomberg New Energy Finance’s energy expert and global head of strategy says the long delay and cost blowout at Flamanville 3 is not an isolated incident.

“Very similar delays and multifold cost blowouts have occurred with recent reactor builds in the UK, Finland and USA,” Bhavnagri writes on LinkedIn.

“Countries with well established nuclear industries.

“The lesson here? Don’t believe anyone who says they know how much it will cost and how long it will take to build a new nuclear plant (unless they are in China).”

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by
Tags: nuclear

Recent Posts

Solar Insiders Podcast: Why new rules for networks signal a new dawn for consumers

AEMC commissioner Rainer Korte on what the new rules on reporting and data sharing will…

17 July 2026

Developer lands “complete funding package” to begin building state’s largest solar-battery hybrid

Developer says it is good to go on early works and construction of the largest…

17 July 2026

“A really big game-changer:” AEMO looks to battery inverters as syncons prove expensive and hard to find

AEMO says proof that grid forming battery inverters can deliver heartbeat of the grid will…

17 July 2026

Twiggy Forrest’s Squadron abandons plan for troubled New England wind farm

Days after lodging new plans for a more than 500 MW wind farm, Squadron dumps…

17 July 2026

Energy Insiders Podcast: Is Australia on target for a “step change” in energy?

AEMO’S head of systems Nicola Falcon on the 2026 ISP and the importance of grid…

17 July 2026

Australia’s solar PV recycling plans on hold after flagship pilot project suspended

Flagship pilot program to set up 100 sites around the country to collect used solar…

17 July 2026