Hazelwood battery charges up for first time at site of former coal generator

Published by

A second very large battery began operations for the first time on Australia’s main grid this week as the country’s transition from fossil fuel based generation to wind, solar and storage made new milestones.

The 150MW, one hour Hazelwood battery is being built near the site of the brown coal generator that – controversially – shut down in early 2017 with little notice, setting in train a period of high power prices and political outrage.

The battery finished construction a few weeks ago and – like the 250MW, one hour Torrens Island battery in South Australia that charged up for the first time on Wednesday – started operations in the same week that the Liddell coal plant in NSW gradually shut down its last remaining units.

The Hazelwood battery is a joint venture of Engie, the French energy giant that owned the Hazelwood coal plant and owns 70 per cent of the project, and Eku Energy, the newly formed big battery subsidiary from Macquarie’s Green Investment Group, which owns 30 per cent.

“Hazelwood completed construction completion a few weeks back and has been in early stage commissioning for a few weeks now,” Eku Energy’s Daniel Burrows told RenewEconomy.

Source: PocketNEM.

“We are currently moving through hold point testing with AEMO. A big focus for the Engie, Eku Energy and Fluence team is on ensuring the system gets commissioned safely in conjunction with rehab works going on at Hazelwood.

“We are working well with AEMO and (network company) AusNet who have obviously been supportive of getting another 150MW of capacity in the market.”

Hazelwood will initially play in the grid services market, hence the short amount of storage, but as the market for arbitrage grows, and as more coal fired power stations retire, the battery will likely be extended to four hours duration or more, and possibly bigger capacity too.

Hazelwood and Torrens Island are just two of a number of new big batteries that are under construction and soon to be connected to the grid.

These include the Bouldercombe battery in Queensland, the Broken Hill battery in NSW, and the Riverina battery complex in south-west NSW, the Chinchilla battery in Queensland and the Capital battery in the ACT, and the Tailem Bend battery in South Australia.

See RenewEconomy’s Big Battery Storage Map of Australia

And our Web Story on the subject.

 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Origin wants to supersize the Eraring battery to make it easily the biggest in the country

Origin Energy seeks approval for new addition to its Eraring battery that would take the…

5 October 2026

Going full hybrid: Massive, $2 billion solar and battery proposed at site of newly expanded wind farm

More projects are going hybrid: A $2 billion solar and battery addition is proposed to…

5 October 2026

Where’s Evo? The missing network in Canberra’s bold electrification experiment

Canberra is becoming a real-world laboratory for mass electrification, but its local electricity network will…

5 October 2026

Not a “dealbreaker:” Big Victorian wind project doesn’t need VNI West

The Macorna wind project will have a simpler ride through state planning, and insists it…

4 October 2026

Huge 195-tonne transformer arrives at big battery site after 1,300 km road trip

One of the heaviest and longest road trips ever undertaken in Australia's energy transition has…

4 October 2026

Australia is making big bets on a slow transition, but the technology S-curve tells a different story

Australia has a choice between investing in the future we can already see – or subsidising…

4 October 2026