Hazelwood battery charges up for first time at site of former coal generator

Published by

A second very large battery began operations for the first time on Australia’s main grid this week as the country’s transition from fossil fuel based generation to wind, solar and storage made new milestones.

The 150MW, one hour Hazelwood battery is being built near the site of the brown coal generator that – controversially – shut down in early 2017 with little notice, setting in train a period of high power prices and political outrage.

The battery finished construction a few weeks ago and – like the 250MW, one hour Torrens Island battery in South Australia that charged up for the first time on Wednesday – started operations in the same week that the Liddell coal plant in NSW gradually shut down its last remaining units.

The Hazelwood battery is a joint venture of Engie, the French energy giant that owned the Hazelwood coal plant and owns 70 per cent of the project, and Eku Energy, the newly formed big battery subsidiary from Macquarie’s Green Investment Group, which owns 30 per cent.

“Hazelwood completed construction completion a few weeks back and has been in early stage commissioning for a few weeks now,” Eku Energy’s Daniel Burrows told RenewEconomy.

Source: PocketNEM.

“We are currently moving through hold point testing with AEMO. A big focus for the Engie, Eku Energy and Fluence team is on ensuring the system gets commissioned safely in conjunction with rehab works going on at Hazelwood.

“We are working well with AEMO and (network company) AusNet who have obviously been supportive of getting another 150MW of capacity in the market.”

Hazelwood will initially play in the grid services market, hence the short amount of storage, but as the market for arbitrage grows, and as more coal fired power stations retire, the battery will likely be extended to four hours duration or more, and possibly bigger capacity too.

Hazelwood and Torrens Island are just two of a number of new big batteries that are under construction and soon to be connected to the grid.

These include the Bouldercombe battery in Queensland, the Broken Hill battery in NSW, and the Riverina battery complex in south-west NSW, the Chinchilla battery in Queensland and the Capital battery in the ACT, and the Tailem Bend battery in South Australia.

See RenewEconomy’s Big Battery Storage Map of Australia

And our Web Story on the subject.

 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Miners are burning a lot more diesel than four years ago, just for same amounts of now hard-to-get coal

The mining industry is burning even more diesel for the same amount of production as…

21 May 2026

Spanish energy giant sends first of two forest-based wind farms into federal green queue

Spanish energy giant seeks planning approval for the first of two wind farms it is…

21 May 2026

Cannon-Brookes bankrolls one of biggest batteries in the world, in huge bet on thermal storage

Grok Ventures investment allows US thermal storage company to go ahead with its first gigawatt-scale…

20 May 2026

Some of Australia’s dirtiest coal mines are about to change hands. Here’s why we should be worried

Some of Australia's most emissions-intensive coal mines have used some of its most sophisticated methane…

20 May 2026

“Island-able” solar-battery microgrid wins funding to keep lights on in town at the end of the line

Arena will help fund the development of a solar and battery microgrid that will provide…

20 May 2026

Solar will be largest power generator in “much changed” world by 2032, but battery storage is the big mover

BNEF's latest annual New Energy Outlook details a "much changed" global market, spurred by energy…

20 May 2026