Hazelwood battery charges up for first time at site of former coal generator

Published by

A second very large battery began operations for the first time on Australia’s main grid this week as the country’s transition from fossil fuel based generation to wind, solar and storage made new milestones.

The 150MW, one hour Hazelwood battery is being built near the site of the brown coal generator that – controversially – shut down in early 2017 with little notice, setting in train a period of high power prices and political outrage.

The battery finished construction a few weeks ago and – like the 250MW, one hour Torrens Island battery in South Australia that charged up for the first time on Wednesday – started operations in the same week that the Liddell coal plant in NSW gradually shut down its last remaining units.

The Hazelwood battery is a joint venture of Engie, the French energy giant that owned the Hazelwood coal plant and owns 70 per cent of the project, and Eku Energy, the newly formed big battery subsidiary from Macquarie’s Green Investment Group, which owns 30 per cent.

“Hazelwood completed construction completion a few weeks back and has been in early stage commissioning for a few weeks now,” Eku Energy’s Daniel Burrows told RenewEconomy.

Source: PocketNEM.

“We are currently moving through hold point testing with AEMO. A big focus for the Engie, Eku Energy and Fluence team is on ensuring the system gets commissioned safely in conjunction with rehab works going on at Hazelwood.

“We are working well with AEMO and (network company) AusNet who have obviously been supportive of getting another 150MW of capacity in the market.”

Hazelwood will initially play in the grid services market, hence the short amount of storage, but as the market for arbitrage grows, and as more coal fired power stations retire, the battery will likely be extended to four hours duration or more, and possibly bigger capacity too.

Hazelwood and Torrens Island are just two of a number of new big batteries that are under construction and soon to be connected to the grid.

These include the Bouldercombe battery in Queensland, the Broken Hill battery in NSW, and the Riverina battery complex in south-west NSW, the Chinchilla battery in Queensland and the Capital battery in the ACT, and the Tailem Bend battery in South Australia.

See RenewEconomy’s Big Battery Storage Map of Australia

And our Web Story on the subject.

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024

Solar Insiders Podcast: A roller coaster year in review – and the keys to a smoother 2025

In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…

20 December 2024

CEFC creates buzz with record investment in poles and wires, as Marinus bill blows out again

CEFC winds up 2024 with record investment in two huge transmission projects, as Marinus reveals…

20 December 2024

How big utilities manipulate the energy market, even with a high share of wind and solar

Regulator says big energy players are manipulating prices to their benefit. It's not illegal, but…

20 December 2024

“Precipitous:” Builder of Australia’s biggest battery sees big cost falls, compares grid to “pearl necklace”

The builder of Australia's biggest battery project describes the country's long stringy grid as like…

20 December 2024

New wind output record arrives in time for evening peak, solar record beaten too

Australia's biggest coal grid witnesses record output of wind energy - in the evening peak.

20 December 2024