Governments

Gupta wins approval for Playford big battery, key part of ambitious solar plan

Published by

A 100MW/100MWh battery that forms a key part of Sanjeev Gupta’s ambitious plans to power South Australia’ manufacturing sector with solar and storage – has won development approval from the state government.

The Playford Utility Battery (PUB) project – located near the former coal fired generator in Port Augusta that shared its name – this week received approval from the South Australian planning minister Stephan Knoll.

Project developer Simec Energy Australia, majority owned by Gupta’s GFG Alliance, says this a substantial step towards the commencement of construction, and for its plans to invest $1 billion in

The Playford battery has a nominal capacity of 100MW/100MWh, but output can be pushed to 135MW in periods of high demand. This compares to the Tesla big battery at Hornsdale, which has a nominal capacity of 100MW/129MWh.

The Playford battery will provide both FCAS and Fast Frequency Response services to the National Electricity Market and will take advantage of market arbitrage opportunities, and the price differential between high and low electricity demand periods. It should be noted, however, that the FCAS market cake is now beginning to shrink as more batteries enter the network.

“Securing Development Approval is another important milestone in Simec Energy Australia’s work to invest US$1Billion to deliver 1GW of vital dispatchable renewable energy to the National Electricity Market,” CEO Marc Barrington said in a statement.

“Delivering this important firming asset into the National Electricity Market will provide greater stability and enable Simec Energy Australia to provide globally competitive energy to our customers. The battery will provide significant benefits for the region and energy users who partner with SIMEC Energy Australia for their energy needs.”

“This asset is also being considered under the ARENA Advancing Renewables Program. This funding, if realised, will bring this project to life – enabling its delivery – as well as continuing to enhance retail electricity competition within South Australia.”

The Playford Utility Battery is to be built just outside of Port Augusta in South Australia, and when completed, will rank amongst the biggest battery storage systems in the world.

The Hornsdale Power Reserve, the Tesla battery’s official title, has proven to be both highly profitable and substantially reduced the cost of FCAS and frequency response services through the use of large-scale battery storage.

The Playford project follows Simec’s 280MW Cultana Solar Farm in Whyalla, which won planning approval in May, with the solar project set to include its own battery storage system.

There is also a major pumped hydro project near Whyalla, which is seeking support under the federal government’s UNGI – Underwriting New Generation Investment initiative. But nothing has been heard of it since before the federal election, probably because the Coalition was not expecting to win it.

Simec sees battery storage projects like Playford as helping to support an enabling environment for the increased deployment of variable renewable energy projects, like the Cultana solar farm.

Gupta has pledged to invest up to $1 billion in clean energy projects in South Australia, which will be used to compliment the GFG Alliance’s investments in the Whyalla steelworks that the consortium acquired in 2017, as well as the potential to manufacture of electric vehicles in Australia.

Simec’s Barrington was interviewed about the company’s plans in Whyalla and Port Augusta on RenewEconomy’s Insiders Podcast. Click here to listen to that podcast.

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.
Michael Mazengarb

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.

Recent Posts

“A weapon for deep sea wind power:” Goldwind rolls out first 22MW offshore turbine

Goldwind says its first 22 ME offshore wind turbine will be a "weapon" on costs,…

18 December 2024

Solar swing state: From nearly too much grid demand to warnings of not enough in less than a day

In less than 24 hours Victoria went from having record demand to warnings of having…

18 December 2024

Zen inks deal with pumped hydro and hyrogen hopeful to help large energy users kick fossil habit

Zen Energy signs memorandum of understanding to develop a smart software based "24/7 Sustainable Energy…

18 December 2024

Renew Economy is changing our reader comments platform

From December 19, 2024, Renew Economy will be changing its article comment platform. And for…

18 December 2024

Solar farm and battery emerge from rhombus of regret with bank finance and a construction plan

Financial close has been reached for a long awaited solar and battery project pitched originally…

18 December 2024

UK-based Cubico closes deal with banks for 500MW wind project, its first in Australia

One of world's largest privately owned renewable energy developers reaches financial close on 500 MW…

18 December 2024