Graph of the Day: Broken Hill Solar Plant achieves full generation

Published by

Less than a week after the last PV modules were installed at AGL Energy’s Broken Hill Solar Plant, Australia’s second largest solar plant – after its sister plant, Nyngan – has achieved full capacity, sending 53 MW of renewable energy into the National Electricity Market.

As you can see in the graph below, the plant, located in western NSW, reached its capacity output just before midday. It is expected to produce enough renewable energy to power 17,000 homes a year.

When combined with the 102MW Nyngan Solar Plant, also in western NSW, the completed Broken Hill Solar Farm will help produce approximately 360,000MWh of electricity annually – enough to power 50,000 average Australian homes.

 

“The momentum at our Broken Hill project has been really building,” said AGL’s gead of group operations, Doug Jackson. “We installed the last of the 677,760 solar photovoltaic (PV) modules on Monday and have been pre-commissioning sections in preparation.

“We are still progressing final commissioning and testing with the aim of being fully operational by early December,” he said.

This is another graph, showing the combine output of the solar plants in both Nyngan and Broken Hill on the National Electricity Market.

Further details, including live updates, can be found here.

Acting ARENA CEO Ian Kay said the completion sent a positive signal for large-scale solar in Australia, noting that expressions of interest for ARENA’s $100 million large-scale solar round closed on Tuesday.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Huge 195-tonne transformer arrives at big battery site after 1,300 km road trip

One of the heaviest and longest road trips ever undertaken in Australia's energy transition has…

4 October 2026

Australia is making big bets on a slow transition, but the technology S-curve tells a different story

Australia has a choice between investing in the future we can already see – or subsidising…

4 October 2026

One of Australia’s biggest wind farms forced to revisit off-take deals after lengthy construction delays and repairs

The lengthy delays at what would have been the country's biggest wind farm have forced…

3 October 2026

Still in the dark: Snowy Hydro’s awkward anniversary marked without promised review of Snowy 2 costings

The public remains largely in the dark about the full cost of the giant Snowy…

3 October 2026

Energy Insiders: Australia’s diesel dependence is not normal

Amandine Denis-Ryan from IEEFA on what can be done about Australia's unique and unhealthy dependence…

2 October 2026

September was Australia’s second hottest on record, and second driest in the east, BoM data shows

For maximum readings, September came in as Australia's third warmest. For minimums, last month narrowly…

2 October 2026