Granville Harbour wind farm nears first generation in Tasmania

Published by

A 112MW Tasmanian wind farm that promises to deliver a one-third increase to the state’s wind power capacity is set to start sending power to the grid in December, as the first of 31 turbines nears completion.

The $280 million Granville Harbour Wind Farm is being developed by Palisade Investment Partners on a cattle farm on Tasmania’s west coast, where it will tap that region’s famous roaring forties winds, which blow in from the Southern Ocean.

An update on the project early this month said construction activities were progressing well, with eight wind turbine foundation concrete pours complete, and the first turbine on track to be built by the end of October.

Reports in the local press late last week reported a new milestone, with the first steel component lifted into the air – putting the first turbine on track for completion in late November, and first commercial generation in December.

“…That was a big deal for many of us because it is the first time in nearly 18 months that we’ve been digging holes out there that we’ve got above ground,” project director Lyndon Frearson told the Burnie Advocate.

The wind farm also opened up to the public last week, to give locals a chance to view one of its 62 metre long turbine blades before it is put to work at the top of the tower.

“People have been hearing about it for a long time and to see the blade coming through, it’s sort of the first big, tangible sense of yep, there’s a wind farm coming,” Frearson said.

As we have reported, the wind farm reached financial close in July last year, after a $59 million investment from the Clean Energy Finance Corporation.

The project was initially being developed by Westcoast Wind, which was bought out by Palisade in February 2018, some months after the two companies negotiated a long-term PPA for the wind farm’s output with Hydro Tasmania.

Hydro Tasmania says Granville Harbour will contribute to its plans to double the Apple Isle’s renewable energy capacity and make it the Battery of the Nation.

The wind farm will be connected to the Tasmanian grid via a new 11km transmission line that will join up to a connection point at the existing Reece Dam.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Seize the day: Time to let solar “daylight saving” in batteries reduce our costs in Australia

Well-designed reforms are needed to accelerate the shift away from the exposure to oil and…

2 April 2026

Governments urged to share costs of gas network death spiral, as rule maker lays down the law

Calls for governments to get their plans – and subsidies – in order, as the AEMC…

2 April 2026

Huge solar and battery project shrugs off long-distance objectors with IPC approval

A huge solar and battery project been given the green light by the independent planning…

2 April 2026

First transmission tower finally goes up in NSW’s first renewable energy zone

The first transmission tower in the first renewable energy zone is now up.

2 April 2026

Giant copper project signs deal for Australia’s biggest off-grid hybrid renewables facility

One of Australia's biggest copper mining projects to be powered by largest off-grid hybrid renewables…

2 April 2026

Rebate bonus: Rooftop solar charts stunning new installation record, spurred by home battery boom

Rooftop solar charts record month of newly installed capacity across Australia, in a stunning reversal…

2 April 2026