Solar

Goulburn community solar farm cuts ties with Siemens over Adani coal connection

Published by

One Step Off The Grid

A 1.8MW community solar and battery project planned for development in the NSW Southern Tablelands town of Goulburn has hit a minor snag after cutting ties with its inverter supplier, Siemens, over the latter’s support of the massive Adani coal mine in Queensland.

Community Energy for Goulburn, or CE4G, is building a community-owned solar farm in Goulburn, supported by a grant from the NSW government, and financed by local community investors keen to keep the profits in the local community.

As One Step reported in March, the project has come a long way since CE4G was set up four years ago, with the aim of building a 1MW(AC) solar farm that could be co-owned by residents for as little as $400 a share.

In August last year, the group secured a contract with local outfit Komo Energy for development services of the now-bigger solar farm. And in March, the plans to add a 400kW/800kWh battery storage system were announced.

But CE4G said on Wednesday that it had told Siemens it was not prepared to use its inverters for the solar farm since the German multi-national had signed up to supply signalling equipment for the rail line being built to service Adani’s controversial Carmichael coal mine.

This was despite Siemens having the “most convenient” inverter solution for combining the project’s solar and battery within a very specific output mandated by Essential Energy, the group’s vice president, Ed Suttle, said.

“Even though Siemens have the right equipment for our particular application, we can’t see any point in trying to reduce the Goulburn community’s carbon footprint while using equipment from a company which is helping Adani cancel out all our efforts,” said CE4G’s Suttle.

“So we have been forced to redesign the project because we are simply not prepared to support a company that is deeply involved with the Adani mine,” he said.

Suttle told One Step on Thursday that the project was still on track to be completed and switched on in mid-2021, and that this “moral decision” – while having some implications in the project’s design – would add two-three weeks at most to the process. CE4G was unable to say at this point who the new inverter supplier would be.

To read the full story on RenewEconomy sister site One Step Off The Grid click here…

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

One of Australia’s biggest battery project seals new contracts with renewable-focused energy retailers

Neoen seals two new "virtual" contracts with energy retailers for what will be one of…

18 June 2026

“Too complex, too hard, too often unfair:” Plan to reform electricity pricing backs contentious tariff changes

AEMC pushes ahead with a hotly contested recommendation to reform how network costs are recovered…

18 June 2026

We’re targeting 35 pct electrification in less than 10 years – but 35 pct of what?

The COP31 co-presidents had the idea right on global electrification targets. They got the measurement…

17 June 2026

Investors still “largely downbeat” about renewables, as policy and fossil risks overshadow rewards

Headline policy reform has not translated into improved investment conditions for renewables in Australia, a…

17 June 2026

“Pouring oil on climate fire:” Global fossil fuel use must halve by 2035 to avoid catastrophic climate damage

Global fossil fuel use must halve by 2035 and be phased out entirely by 2070…

17 June 2026

Must do better: Bowen seeks rule change to force energy retailers to do right thing by electricity customers

Federal energy minister seeks principles-based rule change to ensure retailers are doing more than just…

17 June 2026