Goulburn community solar farm cuts ties with Siemens over Adani coal connection

Published by

One Step Off The Grid

A 1.8MW community solar and battery project planned for development in the NSW Southern Tablelands town of Goulburn has hit a minor snag after cutting ties with its inverter supplier, Siemens, over the latter’s support of the massive Adani coal mine in Queensland.

Community Energy for Goulburn, or CE4G, is building a community-owned solar farm in Goulburn, supported by a grant from the NSW government, and financed by local community investors keen to keep the profits in the local community.

As One Step reported in March, the project has come a long way since CE4G was set up four years ago, with the aim of building a 1MW(AC) solar farm that could be co-owned by residents for as little as $400 a share.

In August last year, the group secured a contract with local outfit Komo Energy for development services of the now-bigger solar farm. And in March, the plans to add a 400kW/800kWh battery storage system were announced.

But CE4G said on Wednesday that it had told Siemens it was not prepared to use its inverters for the solar farm since the German multi-national had signed up to supply signalling equipment for the rail line being built to service Adani’s controversial Carmichael coal mine.

This was despite Siemens having the “most convenient” inverter solution for combining the project’s solar and battery within a very specific output mandated by Essential Energy, the group’s vice president, Ed Suttle, said.

“Even though Siemens have the right equipment for our particular application, we can’t see any point in trying to reduce the Goulburn community’s carbon footprint while using equipment from a company which is helping Adani cancel out all our efforts,” said CE4G’s Suttle.

“So we have been forced to redesign the project because we are simply not prepared to support a company that is deeply involved with the Adani mine,” he said.

Suttle told One Step on Thursday that the project was still on track to be completed and switched on in mid-2021, and that this “moral decision” – while having some implications in the project’s design – would add two-three weeks at most to the process. CE4G was unable to say at this point who the new inverter supplier would be.

To read the full story on RenewEconomy sister site One Step Off The Grid click here…

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

“It’s time to switch it on:” How to unlock a commercial rooftop PV power station equal to 10 coal plants

Months-long grid connection delays and costs that up to six times higher than originally quoted…

3 August 2026

Green bank targets small solar hybrids and battery retrofits in new $100 million package as mega projects stall

New CEFC funding campaign focuses on small solar hybrids and battery retrofits, which can be…

3 August 2026

Energy Insiders Podcast: A battery with every wind turbine

Goldwind's John Titchen explains why and how all new wind turbines could come with their…

31 July 2026

Origin reports big dip in gas sales, as demand falls and batteries grab more of energy mix

Australia’s biggest energy retailer reports significant dip in gas sales, as customer demand falls and…

31 July 2026

Two coal state energy ministers come face to face and present wildly different visions of the future

The energy ministers of Australia's two most coal dependent states come face to face. One…

31 July 2026

Labor’s flagship renewable energy scheme has not worked: It’s time to replace the CIS with a CFD

The CIS has not worked. But the capacity it was designed to procure is needed…

31 July 2026