Storage

Giant Canberra battery gets approval to help wean national capital off fossil gas

Published by

A giant battery project that will help get the national capital get off gas and reach its target of net zero by 2045 has won development approval and is expected to begin construction later this year.

The 250 MW, 500 MWh Williamsdale battery – part of what is known as the Big Canberra Battery – is being built on the outskirts of the national capital.

The ACT has already reached 100 per cent net renewables through a series of contracts with wind and solar farms, but is contracting more renewable energy projects and a series of big battery projects to support the electrification of transport and homes, which will require more grid power.

The ACT has the highest uptake of electric vehicles in the country, running at more than 20 per cent of new car sales, and has banned the installation of gas networks in new housing developments and is working to wean existing homes off fossil gas appliances.

Two big batteries have already been built in Canberrans – the 10MW/20MWh Queenbeyan battery owned by GPG is already operating, while the 100MW/200MWh Capital battery owned by Neoen is finally going through its commissioning phase after major delays in obtaining connection approvals.

The Williamsdale battery is being built by Eku Energy, an offshoot of Macquarie Group that has already built the Hazelwood battery in Victoria and is building the Rangebank battery in the same state.

Eku Energy has struck an innovative financing deal with the ACT government for the battery and will receive quarterly payments over 15 years, to provide revenue certainty and help lower the cost of capital, and will share profits from the merchant operations of the battery with the government in return.

“We’ve achieved a new milestone today with the approval of the Development Application for the Williamsdale Battery Energy Storage System,” Eku Energy said in a LinkedIn post on Wednesday.

The Williamsdale Battery is expected to cost between $300 and $400 million. Construction will start in late 2024 with completion expected in 2025.

See RenewEconomy’s Big Battery Storage Map of Australia

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Energy Insiders: Australia’s diesel dependence is not normal

Amandine Denis-Ryan from IEEFA on what can be done about Australia's unique and unhealthy dependence…

2 October 2026

September was Australia’s second hottest on record, and second driest in the east, BoM data shows

For maximum readings, September came in as Australia's third warmest. For minimums, last month narrowly…

2 October 2026

Chart of the day: Ten years of diesel rebates almost pays for a new truck

Diesel fuel tax credits earned over 10 years nearly equate the price of a huge…

2 October 2026

Biggest wind farm in two years reaches financial close, the ninth in last 12 months, and a new big battery

Updated: The biggest wind farm to reach financial close in Australia in the last two…

2 October 2026

Australian company behind home battery that Bowen bought enters administration, hit by flood of “cheaper” imports

Australian battery maker whose customers include the federal energy minister has gone into voluntary administration,…

2 October 2026

Environmental approvals process kicks off for giant transmission line Coalition has vowed to scrap

A major new transmission line that the state opposition has vowed to scrap is seeking…

2 October 2026