A giant battery project that will help get the national capital get off gas and reach its target of net zero by 2045 has won development approval and is expected to begin construction later this year.

The 250 MW, 500 MWh Williamsdale battery – part of what is known as the Big Canberra Battery – is being built on the outskirts of the national capital.

The ACT has already reached 100 per cent net renewables through a series of contracts with wind and solar farms, but is contracting more renewable energy projects and a series of big battery projects to support the electrification of transport and homes, which will require more grid power.

The ACT has the highest uptake of electric vehicles in the country, running at more than 20 per cent of new car sales, and has banned the installation of gas networks in new housing developments and is working to wean existing homes off fossil gas appliances.

Two big batteries have already been built in Canberrans – the 10MW/20MWh Queenbeyan battery owned by GPG is already operating, while the 100MW/200MWh Capital battery owned by Neoen is finally going through its commissioning phase after major delays in obtaining connection approvals.

The Williamsdale battery is being built by Eku Energy, an offshoot of Macquarie Group that has already built the Hazelwood battery in Victoria and is building the Rangebank battery in the same state.

Eku Energy has struck an innovative financing deal with the ACT government for the battery and will receive quarterly payments over 15 years, to provide revenue certainty and help lower the cost of capital, and will share profits from the merchant operations of the battery with the government in return.

“We’ve achieved a new milestone today with the approval of the Development Application for the Williamsdale Battery Energy Storage System,” Eku Energy said in a LinkedIn post on Wednesday.

The Williamsdale Battery is expected to cost between $300 and $400 million. Construction will start in late 2024 with completion expected in 2025.

See RenewEconomy’s Big Battery Storage Map of Australia

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

China solar giant Jinko seeks federal approval for massive PV and battery project in Queensland

Chinese solar giant Jinko seeks planning approvals for a large solar and battery project near…

27 November 2024

Community meetings for proposed Victoria wind farm cancelled due to “safety concerns”

Community forums for proposed wind farm in central Victoria cancelled by the developer over "safety…

27 November 2024

Australia’s newest and biggest battery charged with surprise role in keeping lights on in NSW heatwave

Updated: Australia's newest and biggest battery makes a surprise intervention on the grid as the…

27 November 2024

NSW consumers asked to dial back electricity use as coal and gas plants go missing in heatwave

NSW asks consumers to dial back electricity use in heatwave as major coal units go…

27 November 2024

Tamworth council backs Greens move to continue fight against contested wind project

Tamworth Regional Council to join legal proceedings to block the Hills of Gold wind farm.

27 November 2024

Ace Power hits go on brave new proposal for a New England wind farm, along with solar and battery

Ace Power launches brave proposal for the New England Hillview wind farm - along with…

27 November 2024