Genex secures funds for Bouldercombe battery, flags more big battery projects

Published by

Renewable energy and storage developer Genex says it wants to grow its portfolio of big battery projects after securing funding to construct its first big battery project in Queensland.

Genex said on Monday it has secured a $35 million debt facility from infrastructure investor Infradebt to fund the construction of the 50MW/100MWh Bouldercombe battery, and is seeking an equity raising for up to $50 million to finance this and other big battery projects.

The deal with Infradebt includes a long-term partnership to finance further big battery projects in Australia that will operate on a merchant basis.

“We are extremely pleased to have reached an agreement with Infradebt for the $35m debt facility for the Bouldercombe Battery Project,” Genex CEO James Harding said in a statement to the ASX on Monday.

“The debt facility allows Genex to retain upside exposure to the attractive economics of energy storage and maximise the economic returns of the project which was an important factor when we considered the appropriate level of gearing and counterparty for the project.”

Harding also flagged a repeat of the innovative off-take arrangements with Tesla that helped pave the way for financing of the Bouldercombe battery.

That deal includes a revenue sharing deal with Tesla  – who will supply both Megapacks for the big battery system and its auto-bidder software. Tesla will operate the battery for the first eight years and provide Genex with guaranteed revenues.

“(That will) allow us to retain upside through innovative offtake arrangements, while continuing to maximise leverage and project economics,” Harding added.

Shares in Genex were placed into a trading halt on Monday, pending further announcements relating to a “material capital raising”, with the company looking to tap shareholders to fund the further expansion of its battery portfolio.

Genex is seeking to raise $40 million through an offer of new shares to institutional investors, but could raise another $10 million in a share purchase plan with existing shareholders.

Around half of the new funds, up to $25 million, would be put towards the Bouldercombe project, fully funding the project – with the remainder being held for use as working capital.

Genex expects to reach financial close on the Bouldercombe project by the end of the current week, with the battery expected to the operational in late 2023.

Genex already has portfolio of two large-scale solar projects – the 50MW Kidston solar project and the 50MW Jemalong solar project – and recently commenced construction of its flagship 250MW/2,000MWh pumped hydro energy storage project at Kidston.

Genex undertook a $90 million capital raising last year to secure its share of the funds needed for the development of the pumped hydro energy storage project – and it is likely that another such capital raise will be forthcoming to fund its ongoing expansion into battery storage projects.

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.
Michael Mazengarb

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.

Share
Published by

Recent Posts

“I would choose the data centre:” Renewable energy boss says firm off-taker deals preferable to CIS

Renewable energy developer says contracts with data centres offer more certainty than CIS, while grid…

3 August 2026

Massive 520 MW battery proposed for historic sheep and cattle station near Canberra

Massive 520 megawatt battery proposed for historic grazing property near Canberra.

3 August 2026

“It’s time to switch it on:” How to unlock a commercial rooftop PV power station equal to 10 coal plants

Months-long grid connection delays and costs that up to six times higher than originally quoted…

3 August 2026

Green bank turns to small solar hybrids and battery retrofits in new $100 million package as mega projects stall

Updated: New CEFC funding focuses on small solar hybrids and battery retrofits, which can be…

3 August 2026

Energy Insiders Podcast: A battery with every wind turbine

Goldwind's John Titchen explains why and how all new wind turbines could come with their…

31 July 2026

Origin reports big dip in gas sales, as demand falls and batteries grab more of energy mix

Australia’s biggest energy retailer reports significant dip in gas sales, as customer demand falls and…

31 July 2026