Genex says flagship pumped hydro project needs more time to lock in partners

Published by

Genex Power has pushed back deadlines for signing off the financing for its flagship pumped hydro energy storage project, but insists that the ground-breaking project is ready to go.

In an announcement to the ASX on Wednesday, Genex said it would miss the September 30 deadline it had set itself to secure financial close for the Kidston Pumped Hydro project, as the company works though the project’s final details, including negotiation with Powerlink on connections to the transmission network.

However, the company told RenewEconomy that the delay did not relate to any substantial issues faced by the project, and that the project remained shovel ready and ‘ready to go.’

The Kidston Pumped Hydro project would be Australia’s first new project of its kind for several decades, and would deliver a substantial 250MW/2,000MWh of energy storage in North Queensland.

The project, which will repurpose two disused mine pits for pumped hydro energy storage, has faced a number of delays over the last year, first triggered by EnergyAustralia temporarily backing out of a deal to purchase power from the facility.

Project partners agreed to extend the deadline for Genex to reach financial close on the project at the start of July, to the end of September, but has again indicated that it needs more time to finalised negotiations with its project partners.

The ASX-listed Genex had previously said that it was targeting a September 30 deadline for financial close, but said it was obligated to updated the market when it became clear it would miss the deadline.

It is still confident of locking in $610 million commitment from the Northern Australia Infrastructure Facility to help finance the project, and it had already agreed provide Genex until January 31 2021 to seal the deal.

Genex added that the Queensland Government, which heads to an election at the end of October, had reaffirmed its commitment to make a $132 million investment in new transmission network infrastructure to support the project. The election is unlikely to impact on the Queensland government’s commitment.

Genex said it was progressing the final stages of negotiations with its preferred equity partner, which would take an ownership stake of up to 50 per cent in the pumped hydro storage project.

“We are pleased that the Queensland Government has reaffirmed their commitment of $132 million to help fund the construction of the Kidston Pumped Storage Hydro Project Transmission Line,” Genex CEO James Harding said.

“The development of the Kidston Pumped Hydro Project will create a peak workforce of over 500 people per annum in regional Queensland, secure power supply to local communities and unlock significant clean energy generation in the region.”

“I would like to thank all stakeholders, particularly NAIF, ARENA, the Queensland Government and Powerlink for their ongoing support of the project as we seek to finalise negotiations on the project financing,” Harding added.

Genex is looking to develop a substantial portfolio of clean energy developments clustered around the Kidston pumped hydro project, including the already operating 50MW Kidston solar plant, which may be expanded with an additional 270MW solar project and 150MW of wind power capacity.

Genex also already operates the 50MW Jemalong solar project, and will expand its storage portfolio through its ‘Como Project’ strategy, which will start with a 50MW/75MWh big battery at Bouldercombe in Queensland, for which it recently secured a land access deal with Powerlink.

The price of Genex shares fell slightly on the open of trading on Wednesday following the announcement, dropping around 2 per cent to 20.5 cents per share.

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.
Michael Mazengarb

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.

Share
Published by

Recent Posts

Turbines and transmission towers up and concrete foundations poured at rare state-owned wind farm

State-owned wind farm marks a "huge few weeks of milestones" including delivery of transformers, erection…

13 July 2026

One of Australia’s biggest renewables developers seeks to build one of country’s biggest new gas plants

Plans for one of the nation's biggest new gas plants join the queue for federal…

13 July 2026

Regulator bans two solar and battery installers for failing to meet standards and regulations

Regulator says two individuals banned from installing solar PV and home batteries under the SRES…

13 July 2026

Andrew Forrest’s Squadron Energy unveils another big wind project near crowded renewable zone

Squadron's latest wind project located just outside of crowded renewable zone, and will seek to…

13 July 2026

“We can save at least 20 pct:” Developers rethink how they build giant wind projects

Developers say splitting up EPC contracts for giant wind projects is saving money and lowering…

13 July 2026

Starting from scratch on nuclear in Australia would take longer, cost more than first-time offshore wind

CSIRO says nuclear power is "most expensive in each case" of its modelling, with a…

13 July 2026