Storage

Genex remains upbeat on pumped storage in result dented by solar plant outage

Published by

Australian renewables developer Genex Power has delivered a first-half FY2020 result dented by a “one-off plant outage” at the company’s 50MW Kidston solar project in October that hit revenue and generation from the Northern Queensland Project.

The company said on Friday that the outage, which was caused by a software issue that has since been rectified, had resulted in a 21 per cent decrease in power sent to the NEM across the half-year, while net revenue for the period totalled $A8.7 million.

But Genex was upbeat about the progress of its huge pumped hydro plans at Kidston, which it said “remained an outstanding opportunity for large scale energy storage.”

Genex is still looking for an off-take partner for its 250MW Kidston Pumped Storage Hydro Project (K2-Hydro), which will have eight hours of storage, after a deal with EnergyAustralia deal came apart at the start of November.

The ASX-listed company said it was still in talks with key stakeholders on the pumped hydro project, including EnergyAustralia and the federal and state governments.

The project has backing from the federal government’s North Australia Infrastructure Facility, and from Japanese energy giant J-Power, pending the successful signing of a new off take agreement.

In the meantime, Genex also had some significant wins over the half-year, including reaching financial close on the 50MW Jemalong solar project via a “world-first” green financing deal covering both the ready-to-build NSW project and the existing Queensland Kidston solar farm.

During the period the company also announced the completion of a capital raising of $21.5 million to fund the development of the Jemalong project.

“The past six months have continued to see the company progress and deliver on a number of major milestones in our strategy to become a diverse renewable energy and storage company,” said Genex CEO James Harding.

“The financial close and commencement of construction at the Jemalong Solar Project represents the next step in the company’s growth.”

“(The) refinance of the Kidston Solar One project with a $192 million project funding package was a significant achievement in the half.”

“The 100MW portfolio financing incorporated the largest Certified Green Loan by an Australian renewable energy group, highlighting the quality of the underlying projects as well as the company’s clean energy credentials.”

On its outlook, Genex said it was in a strong position to deliver clean, renewable, power to help Australia meet its renewable energy targets.

“The increasing impact of intermittent power on energy prices highlights the need for large scale storage options such as K2-Hydro,” the company said in its results statement.

Near-term focuses would include delivering steady-state operation and improving overall plant performance of the existing Kidston solar plant, and working to finalise offtake arrangements and financial close for the pumped hydro project.

Genex last year selected Beon Energy Solutions, a unit of Victoria Power Networks, for the Engineering, Procurement and Construction (EPC) contract and an Operation and Maintenance (O&M) contract with Beon Energy Solutions (Beon) for the Jemalong project, on which construction has commenced.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

New renewables and batteries improve grid reliability outlook, but more needs to get built on time, AEMO says

Immediate threat to the reliability of Australia's main grid has been pushed back into the…

25 August 2026

Post-2030 contract design for new renewables takes shape as working group agrees on firming price caps

Work advances on the design for key post -2030 contracts for new renewables and firming…

24 August 2026

Hefty network fees discussed as state government reveals massive scale of data centre grid connection demands

Some of the date centre proposals being discussed for NSW are among the largest in…

24 August 2026

“A Trojan horse for communism!” More big batteries head for review as familiar long distance objectors pile in again

Two more big batteries head for independent review as familiar long distance objectors file the…

24 August 2026

Linking electricity and safeguards could make wind projects viable, and oblige gentailers to actually Do Something

Linking the electricity grid with the safeguards mechanism would send clear price signal for wind…

24 August 2026

Australia’s biggest data centre to require 4 substations, 2 power lines, some batteries and 4 days of diesel backup

The massive 800 MW data centre will need city-scale electrical infrastructure, and will install enough…

24 August 2026