Renewables

Genex names contractor for first stage of grid’s biggest solar and battery project

Published by

Listed renewable energy and storage developer Genex Power has named the preferred contractor for the first stage of what is currently set to be the biggest solar and battery storage complex on Australia’s main grid.

Genex says it has chosen PCL Contractors as the preferred firm to build the proposed 775 MW Bulli Creek stage one solar farm, which – depending on timing – will be the largest solar project on the country’s main grid.

It will likely get bigger too, with a total of 2 GW of solar and battery storage capacity planned for the project in the state’s south. The project is jointly owned with Japan’s J-Power.

Genex says it has also begun the tender process for for the first battery stage of the Bulli Creek project, which it currently envisages to be sized at 400MW and four hours storage (1,600MWh), although this will largely depend on the result of off-take discussions.

However, the first solar stage of the project is not locked in, with Fortescue Metals still yet to commit to the Gibson Island green hydrogen project that had signed up to take half the output (337.5 MW) of the Bulli Creek project.

The fate of Gibson Island is likely to depend on the success of Fortescue’s negotiations with state and federal governments. It has argued that Australian green hydrogen projects need help because of the relatively high cost of electricity. A decision is expected by the end of this month.

Genex has been pursuing off-take agreements which will ultimately influence the size of the project, and it has been working on grid connection studies that it has submitted with the state transmission company Powerlink.

Meanwhile, Genex has released its revenue details for the December quarter, in which it earned $5.3 million from electricity from its two operating 50 MW solar farms – at Kidston in Queensland and Jemalong in NSW – and the newly connected 50 MW, 100 MWh Bouldercombe big battery in Queensland.

Genex says revenue for the two solar project fell significantly in the latest quarter as wholesale electricity prices also fell.

The Kidston solar farm, normally one of the strongest solar assets in the country, suffered significant economic constraints when the daytime price fell below zero, and averaged just $54/MWh for the quarter.

Jemalong, which also earns money from the sale of Large Scale Generation Certificates (Kidston’s LGCs go to the state government under an underwriting deal), was more able to duck and weave around the price volatility and was able to pocket an average of $79/MWh during the quarter, with more than half of this coming from LGCs.

Meanwhile, the Bouldercombe battery earned $1.1 million in the few weeks it was operational in December (it became fully operational on December 12), collecting an average net price of $311/MWh selling into the evening peaks.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Contract awarded for concrete foundations and early works for ten massive spinning machines

Contracts awarded for concrete foundations and other early works for ten huge spinning machines required…

22 July 2026

Rinehart-backed miner achieves 90 pct renewables in June quarter, may take processing plant off grid

Mine backed by net zero opponent Gina Rinehart achieved 90 per cent renewable share in…

22 July 2026

Network seeks partners on upgrade to nation’s largest isolated grid, to cram in more renewables

State-owned utility seeks expressions of interest for project and contract management partners on its massive…

22 July 2026

Can EVs help get more out of the grid, for less? Two new grant winners hope to show the way

New federal government grant package backs 14 projects to get more renewables on the grid,…

22 July 2026

Government backs “disaster proposal” to power 2 GW hyperscale data centre with fracked Beetaloo gas

NT government has set aside land for the $40 billion gas-powered AI ambitions of ASX-listed…

22 July 2026

Solar and battery to deliver 80 pct of remote off-grid gold mining town’s power supply

Transition of an off-grid gold mining town from diesel to mostly solar and battery to…

22 July 2026