Geelong geothermal project in limbo after Victoria pulls funding

Published by

Aspiring geothermal energy developer Greenearth Energy may have to abandon its planned 12MW geothermal energy project for the industrial city of Geelong after the Victorian government withdrew its $25 million grant.

It is the second blow in as many months for Greenearth, which announced in August that an approach for funding from the Australian Renewable Energy Agency (ARENA) had been rejected. It says it is now reviewing its next steps.

The Geelong Geothermal Power Project was to have been located about 11km North West of Anglesea, on the Holcim Ltd Moriac quarry site. The project has three planned stages; drilling to prove the local geothermal resource, constructing a 12 MW demonstration plant, and if the demonstration project amounts, the development of a commercial plant.

The company had previously secured funding from the Victorian State Government for up to $25 million, with $5m for stage 1 and $20m for stage 2.  Part of negotiations with the state government included an extension period and assistance for the company to apply for match funding from the Federal Government.

It said on Tuesday that it had sought negotiations with the Victorian government but had been unable to secure a meeting. It was then told that the grant had been terminated.

“Greenearth Energy is disappointed with the lack of support and commitment shown by the Victorian Government and the Federal Governments ERP to assist in developing this renewable energy project for Victoria and the regional town of Geelong,” it said in a statement.

It said it had invested considerable time and had received “fantastic” support from industry partners (such as ALCOA of Australia, Leighton Contractors, Holcim Australia and The University of Melbourne) and leading engineering consulting firms including Sinclair Knight Merz and Hot Dry Rocks.

“It is disappointing to have this funding withdrawn despite positive feedback from these leading geothermal experts and at a stage where the Australian renewable energy sector is looking for ways to progress towards the Australian Federal Government’s target of a 5% reduction in CO2 emissions by 2020,” it said.

It said it will continue to look at developing its Latrobe Valley interests, where it is hopeful of extracting geothermal heat from beneath the vast brown coal reserves. It is working with Monash University on that project.

The company is also focusing on the industrial energy efficiency sector in Australia and New Zealand, and CO2 to fuel  conversion markets globally. It said these businesses continue to show positive and growing signs of development.

Managing director Samuel Marks said the company would also look to develop Israeli technology that uses solar thermal energy to CO2 emissions into fuels.

(This story has been updated to say that project is not yet abandoned, although funding has been pulled).

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by
Tags: geothermal

Recent Posts

Australia’s main grid sets new solar output record before rooftop PV takes centre stage

Australia hits a new solar output record in the morning period before rooftop solar takes…

24 February 2025

Fossil fuel lobby shares global “toolbox of tactics” to fight Victoria’s gas phaseout

Fossil fuel companies in Australia and their industry associations have been swapping notes with their…

24 February 2025

Carbon time bomb: Dutton’s nuclear plan will blow up Paris and emissions targets, CCA says

The Climate Change Authority says a nuclear pathway would add an extra 2 billion tonnes…

24 February 2025

Energy consumers pick up the bill as gas industry prioritises export windfalls

The gas market on the east coast has directly contributed to the cost-of-living crisis. It…

24 February 2025

Victoria solar farm shut down after fire in on-site inverters, must mow grass

Safety regulator closes small Victoria solar farm after inverter fire while it investigates cause and…

24 February 2025

Labor targets wind towers, batteries and electrolysers in $500 million local content support

Labor promises $500 million to ensure locally made steel and aluminium are used in wind…

24 February 2025