Fuel-free spinning machine to help ease more solar into Top End grid

Published by

The government owned utility in the Northern Territory will convert one of the gas turbines at its largest gas fired power station to operate as a synchronous condenser in an effort to increase the amount of renewable energy on the local grid.

The Channel Island power station in Darwin opened in 1986 and originally boasted seven gas turbines and one steam turbine and is due to shut in 2026/27.

But in an effort to accommodate more solar on the local grid, its owner Territory Generation will convert one unit into a syncon, essentially a spinning machine that does not burn fuel but which can still provide essential grid services such as inertia and system strength.

The Northern Territory has a target of 50 per cent renewables by 2030, but apart from a rapid increase in rooftop solar its efforts to accommodate larger scale renewables have come to nought, with four solar farms sitting idle for several years because of the local regulator’s strict connection and bidding rules.

Darwin’s first big battery, the 35MW one hour Darwin-Katherine Battery Energy Storage System (DK BESS), which is expected to be commissioned this year, will help address that problem and a second battery project in the Darwin precinct will follow.

Synchronous condensers are used to maintain system voltage on an electricity grid, producing reactive power and useful for stabilising power produced by renewable energy resources.

Four have already been deployed in South Australia, which already has a 75 per cent share of wind and solar, and more elsewhere in the country’s main grid and network operators are looking to use the turbines in soon-to-close coal fired power stations to perform a similar task.

Essential Services Minister Kate Worden said the synchronous condenser, combined with the battery investments, will stabilise the grid to enable more renewable energy to be connected.

“The Frame 6B turbines have served the power system well over the last 40 years, and Territory Generation is excited to repurpose an existing asset to contribute to the future energy requirements of the power system,” said Gerhard Laubscher, CEO of Territory Generation.

“The Channel Island Power Station synchronous condenser conversion project aligns with Territory Generation’s Fleet Transition Plan while advancing Northern Territory Government renewables and emissions objectives.”

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

State’s stand-alone solar fail: The energy transition should deliver more than a new landlord

Western Power's stand-alone power system program is not an energy transition solution. It is a…

10 July 2026

Energy Insiders Podcast: Electric truck network starts to take shape

Electric trucks are suddenly big news in Australia. We catch up with NewVolt's Anthony Headlam…

10 July 2026

Watchdog warns spike in home battery complaints could damage consumer trust

Home batteries are flying off shelves and the consumer watchdog wants stronger protection to maintain…

10 July 2026

Offshore wind developers pray for bipartisan support ahead of key state election

Victoria's offshore wind developers are much more optimistic than they were a year ago, but…

10 July 2026

State utility bets on Australian-first compressed CO2 “energy dome,” with up to 12 hours of storage

Victoria's Latrobe Valley will soon host a ground-breaking long-duration energy storage facility capable of continuously…

10 July 2026

“It’s nuts:” Wind developer forced to truck giant transformer thousands of kilometres after port refusal

Renewable developer says the refusal of its closest port to handle a giant transformer has…

10 July 2026