Western Australian renewables developer Frontier Energy says its planned Warren Renewable Energy project south of Perth is benefiting from falling prices for both battery storage and solar modules, and it has decided to expand the battery component because of it.
The original definitive feasibility study (DFS) proposed a 120MW solar project for stage one of the Waroona Renewable Energy Project with a four-hour 80MW battery.
However, Frontier Energy recently narrowed its battery technology selection to two potential partners, which it says resulted in a 12 per cent increase in battery duration to approximately 4.5 hours, while also resulting in a reduced capital cost for the battery by around 5 per cent.
It is now contemplating a battery with a nameplate capacity of 80MW/360MWh, up from the originally planned 80MW/320MWh.
“The company is in the fortunate position that the cost of the two largest capital items, solar panels and battery, have fallen significantly since the release of the DFS in February,” said Adam Kiley, Frontier Energy CEO.
“Battery prices have fallen due to a combination of factors, including falling raw materials prices, improvement in supply chain, and reportedly weaker than anticipated demand, resulting in an ample supply of batteries in the current market.
“This unique situation is to Frontier’s advantage, with improved battery capacity resulting in increased duration (approximately 4.5 hours compared to 4 hours in the DFS), increasing Project revenue while at the same time achieving a lower capital cost.
Frontier Energy acquired the Waroona Renewable Energy Project in late 2023, which had already secured development approvals for a 355MW project. The acquisition paired nicely with Frontier’s existing plans for a 120MW dual-fuel peaking plant proposed to use both natural gas and green hydrogen.
The company now controls two grid connections capable of exporting upwards of 1GW to the grid, as well as freehold landholding of 868 hectares for future solar expansion.
Frontier says it is still working on its funding strategy, with both debt financing and strategic partnering processes well advanced.
Located 120 kilometres south of Perth, the Waroona Renewable Energy Project would also be located approximately 11 kilometres from Frontier Energy’s proposed Bristol Springs dual-fuel peaking plant.
Australian households have installed a record number of rooftop solar systems and home batteries so…
Trump administration appears to have bet on the wrong horse, with renewables surging and coal…
Few home battery owners have signed up to join virtual power plants, with concerns about…
Zenith Energy’s Michael Buzzard on the remarkable energy transitions achieved in off-grid mines, and plans…
It is 10 years since South Australia's state-wide blackout: Far from being the end of…
First urban renewable energy zone to host pilot program to demonstrate how social housing tenants…