Frontier expands solar and battery project as tender underlines falling cost for modules and storage

Published by

Western Australian renewables developer Frontier Energy says its planned Warren Renewable Energy project south of Perth is benefiting from falling prices for both battery storage and solar modules, and it has decided to expand the battery component because of it.

The original definitive feasibility study (DFS) proposed a 120MW solar project for stage one of the Waroona Renewable Energy Project with a four-hour 80MW battery.

However, Frontier Energy recently narrowed its battery technology selection to two potential partners, which it says resulted in a 12 per cent increase in battery duration to approximately 4.5 hours, while also resulting in a reduced capital cost for the battery by around 5 per cent.

It is now contemplating a battery with a nameplate capacity of 80MW/360MWh, up from the originally planned 80MW/320MWh.

“The company is in the fortunate position that the cost of the two largest capital items, solar panels and battery, have fallen significantly since the release of the DFS in February,” said Adam Kiley, Frontier Energy CEO.

“Battery prices have fallen due to a combination of factors, including falling raw materials prices, improvement in supply chain, and reportedly weaker than anticipated demand, resulting in an ample supply of batteries in the current market.

“This unique situation is to Frontier’s advantage, with improved battery capacity resulting in increased duration (approximately 4.5 hours compared to 4 hours in the DFS), increasing Project revenue while at the same time achieving a lower capital cost.

Image Credit: Frontier Energy

Frontier Energy acquired the Waroona Renewable Energy Project in late 2023, which had already secured development approvals for a 355MW project. The acquisition paired nicely with Frontier’s existing plans for a 120MW dual-fuel peaking plant proposed to use both natural gas and green hydrogen.

The company now controls two grid connections capable of exporting upwards of 1GW to the grid, as well as freehold landholding of 868 hectares for future solar expansion.

Frontier says it is still working on its funding strategy, with both debt financing and strategic partnering processes well advanced.

Located 120 kilometres south of Perth, the Waroona Renewable Energy Project would also be located approximately 11 kilometres from Frontier Energy’s proposed Bristol Springs dual-fuel peaking plant.

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

Energy Insiders Podcast: Getting the best out of the grid

Energy expert Gabrielle Kuiper on getting the best out of distributed energy resources in the…

29 November 2024

Australian homes could slash energy bills by two thirds by cutting out gas and petrol, AEMC says

Australian households could lower their bills by over two thirds if they fully electrify their…

29 November 2024

In the end, the only blackouts were in the media headlines: But there has to be a better way to do this

Blackout featured prominently in media headlines this week, but not on the grid. But as…

29 November 2024

Trina submits approval for Victoria big battery, as locals campaign against solar and storage projects

Trinasolar and Mint Renewables have now both lodged planning applications for neighbouring big batteries in…

29 November 2024

Australia to reshape manufacturing base as Greens deal excludes fossil fuels from flagship industry policy

Greens make last minute commitment to vote for $22 billion Future Made in Australia policy…

29 November 2024

Andrew Forrest seeks green tick for another wind and battery project as Clarke Creek powers up

Andrew Forrest's Squadron Energy seeks green tick for new wind and battery project in NSW…

29 November 2024