Fortescue says first 2GW electrolyser factory will be too small, plans more

Published by

The new head of Fortescue Future Industries, Mark Hutchinson, says the company’s first hydrogen electrolyser factory, due to come on line in early 2023, will be too small to meet the company’s hydrogen ambitions, are more manufacturing plants are planned.

FFI’s first electrolyser factory, a 2GW facility currently being built at the new Green Manufacturing Hub in Gladstone, was hailed as the world’s biggest when first unveiled last year. But it will make barely a dent in the company’s huge green hydrogen ambitions, which are to produce 15 million tonnes a year by 2030.

“When I think about how big this market is, it’s as big as replacing the entire fossil fuel market in the world, and it’s real now,” Hutchinson told Bloomberg at the sidelines of the federal government’s jobs summit in Canberra last Friday.

“We’ll announce over the next few months some big investments in some plants,” Hutchinson added.

Hutchinson, a former head of GE in Europe, took over the role as head of Andrew Forrest’s ambitious green hydrogen plans early last month, taking over from Julie Shuttleworth.

He has an “operating” budget of more than $1 billion for the current financial year and now heads a team of more than 1,000 that is seemingly growing rapidly.

These include some big names such as former RBA deputy Guy Debelle as his CFO, and former AGL boss Andrew Vesey as head of US operations, and ex CleanCo boss Maia Schweizer as head of the western half of the company’s Australian operations, which includes several massive wind, solar and hydrogen projects.

FFI has signed a series of significant MoUs with companies such as Germany’s E.ON and others, but is yet to finalise those supply deals, and Australia is running into stiff competition from a multiple other countries keen to grab a share of the nascent green hydrogen market.

Fortescue’s green hydrogen business is also going to be bigger than the iron ore market that company founder and major shareholder Andrew Forrest built his billions on.

“Once we get going at scale and just looking at the projects we have, it’s enormous,” Hutchinson said.

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024