Fortescue begins construction of state’s biggest solar farm as it forges ahead on Pilbara “real zero” goal

Published by

Fortescue Metals is moving full steam ahead on its Pilbara renewable energy plans, this week kicking off construction of Western Australia’s largest solar farm, at least for now, and just the latest piece in the iron ore giant’s ambitious decarbonisation puzzle.

Fortescue said on Monday it has started work on the 440 megawatt (MW) Solomon Airport solar farm which, once complete, part of its plans to reach “real zero” by 2030, the uncompromising target set by the company’s founder and executive chair, Andrew Forrest.

The Solomon Airport project adds to the 190 MW Cloudbreak solar farm, a project that is under construction – and around two-thirds complete – in the Pilbara’s Chichester Range, and the nearby 133 MW Nullagine wind farm, on which construction is also underway.

Construction of a proposed 644 MW solar farm at Turner River is expected to get underway later this year, having secured federal environmental approval in January and applied for the state green tick last month.

And there is the 100 MW North Star solar farm, completed in 2024 on a former work site, that marked Fortescue’s first foray into large scale solar.

Once operational, Fortescue says the Solomon, Cloudbreak and Turner River projects – together with the existing 100MW North Star Junction solar farm – will deliver around 1.3 gigawatts (GW) of solar capacity.

“Across the Pilbara, we’re using the region’s sun and wind to generate green power for our sites,” says Fortescue chief Dino Otranto.

“We’re building the solar and wind farms, connecting them through our high-voltage transmission network and backing them with battery storage to provide 24/7 firm power.”

Through Pilbara Energy Connect, Fortescue has also installed more than 480 km of high-voltage transmission lines across the Pilbara – part of a renewable energy network that will extend to more than 620 km, once complete, linking the company’s energy assets to its operations and rail network.

Fortescue says these projects represent one of the largest renewables deployments by any heavy industry company in Australia.

Alongside the ongoing electrification of Fortescue’s heavy industrial machinery and transport, it’s an accomplishment that sets it apart from most others – and shows what can be done when the will is there.

“Importantly, each successive solar project is being delivered more efficiently than the last,” Otranto said on Monday.

“As technology improves and we gain scale, our installed capital intensity continues to come down – strengthening the economics of replacing diesel and gas with renewable energy.”

As Renew Economy reported last month, following a visit to Fortescue’s Pilbara operations, the cost of building solar is already minuscule for the company, at around $40 per megawatt, compared to diesel costs of between $120 and $300 a megawatt. 

But the company continues to strive to get costs down even further, including through an Arena-backed trial of different robotic concepts across its solar portfolio.  

“The real next step in our evolution is you automate that whole process. The automation of a pile driver already exists. Putting a tracker on is very easy to automate, and then the actual installation, the panel is dead simple to automate,” Otranto says. 

“All we’d have to do is put that all together. We’ve been successful in automating massive trucks and running them 2000 kilometers away from the Pilbara. So automating a very simple installation like this would be a no brainer.”

If you would like to join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Data centres to get faster nod if they meet energy, grid and water needs

State says data centres will "need to pay their own way," including bringing additional electricity…

17 August 2026

No, Ray Hadley, the collapse of Zen does not mean renewables have failed, nor that more coal will be burned

Zen Energy's failure has inspired the usual suspects to claim renewables don't work. Curiously, planes…

17 August 2026

“It’s literally life-changing for us:” The drought-stricken farmers looking to wind and solar to secure their future

New England farmers say their future, and their succession plans, depend on their ability to…

17 August 2026

Victoria Coalition says it may keep old coal clunkers running, and will scrap plans to move away from gas

Victoria's Coalition is not ruling out coal extensions and is "throwing open the door" to…

17 August 2026

Wind farm dumped from Australia’s first pumped hydro project in 40 years – due to rocky terrain

Plans to add more solar and a wind farm to delayed pumped hydro project abandoned,…

17 August 2026

We’re trying to win a drag race with the handbrake on: Here are three reforms to deliver the energy transition

Supercharging Australia’s energy system was always going to be complex. But complexity does not need…

17 August 2026