First turbines go up at off-grid mine after 850kms journey from port

Published by

Two months after all of the parts arrived at the remote Western Australia Jundee gold mine, the crane to install them has caught up and the first turbine is being erected.

Renewables developer Zenith Energy says the Goldwind crane has arrived on-site and is now installing the first 165/6.0 megawatt (MW) wind turbine at the site.

The 86 metre-long blades were trucked in from Geraldton Port, via an 850km route that required fences to be taken down and an upgrade to the Wiluna town bypass. 

The 24 MW wind farm complements a 16.9 MW solar farm using 5B solar farm blocks that began generating power last week. 

The microgrid for the remote Northern Goldfields site is backed up by a 12 MW / 13.4 MWh battery, for which commissioning has started, to provide 56 per cent of the site’s power needs. The remainder will be looked after by the existing gas power station. 

Combined, the wind and solar farms are expected to cut the mine’s greenhouse gas emissions by more than half.

The renewables project is underpinned by a power purchase agreement (PPA) between Zenith Energy and mine owner Northern Star Resources, which the miner says will help it “achieve and exceed” its target of a 20 per cent reduction in the carbon intensity of its business by 2025 from a 2020 baseline. A target which includes scope 1, 2 and 3 emissions.

Zenith ticks off Kathleen Valley microgrid

Zenith Energy is also in charge of the Kathleen Valley lithium project in the Western Australia Goldfields area. 

The renewables developer reached commercial operations for the 16MW solar, 17MW/19 MWh battery and 30 MW wind farm last week, a milestone it says marks the finish line for Australia’s largest islanded hybrid power station.

Mine owner Liontown Resources says powering construction and commissioning of the Kathleen mine with renewables might be a first for an Australian mining project, as others tend to ramp up their clean energy generators once production starts. 

Liontown says the system is already powering the on-site accommodation and process plant, and will eventually also power the underground lithium mine, and it expects to beat its initial target of meeting 60 per cent of its supply needs for renewables. 

Some 5MW of diesel standby and 27MW of gas generation were brought online earlier this year, but these will often be switched off and will operate only when the renewable resources are unavailable.

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Rachel Williamson

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Recent Posts

Auditor-general slams management of Snowy 2.0 as more delays loom and project costs blow out

Attorney-general report highlights board and management failings in the blown out Snowy 2.0 project, and…

19 June 2026

Macquarie storage offshoot presents two four-hour battery projects for federal green tick

Storage specialist has nine projects in its portfolio in Australia, with two going public on…

18 June 2026

Frequency penalties are costing some solar farms millions, but this is the market working

Data shows solar farms and big batteries are the biggest loser and winner following changes…

18 June 2026

PV research powerhouse wins fresh Arena funding to pursue ultra-low cost solar

Australia's flagship solar research program has secured another six years of federal funding to continue…

18 June 2026

LGC prices have more than doubled in a few weeks, but who are the buyers – data centres or speculators?

The LGC market is having a moment, doubling in price in a matter of weeks,…

18 June 2026

Demand response trials could open up more than 1 gigawatt of extra grid capacity

This may be one of the most important trials underway today, at least if data…

18 June 2026