First turbines from Silverton wind farm switched on

Published by

The Silverton wind farm

Production from the first two turbines of the 200MW Silverton wind farm near Broken Hill has begun, with the project scheduled to be completed by the middle of the year.

So far, 18 of the 58 turbines have been erected for the $450 million project, which has been a major logistical test given its distance from ports and delivery of the major pieces of hardware such as the turbine blades and nacelles.

The first production from the first two turbines was exported to the grid this past weekend, company officials say.

Silverton is the first major greenfield project of the Powering Australian Renewables Fund (PARF), a  partnership between AGL and QIC to own and develop wind and solar projects.

This video will give an idea of the remoteness in the area, some of the issues transporting the major equipment, and erecting the towers and using helicopters to string the transmission wires.

The project is expected to provide  150 jobs at the peak of construction, many of whom worked on the 53MW Broken Hill solar plant, which PARF also operates, and is located about 25kms away.

Silverton was to be the largest wind farm in NSW, but by the time it gets to 200MW it will likely have already been overtaken by the 270MW Sapphire wind farm in northern NSW, which recently started delivering its first 100MW to the ACT government’s 100 per cent renewable program.

Silverton and the 453MW Cooper’s Gap wind farm in Queensland are listed by AGL as part of the response to the closure to the Liddell coal generator in NSW and together are estimated to have a cost of $62/MWh.

The next three stages of the Liddell replacement will include a 300MW solar farm, battery storage, demand management, an upgrade to the Bayswater coal generator, a new 250MW gas plant, and further storage and renewables projects.

The Silverton wind farm is located in the Barrier Ranges about 25kms west of Broken Hill and will feature 58 GE 3.43-130 wind turbines.

 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Cows and cyclones: New push to design solar farms for cattle and climate, but is Australia ready?

Companies are looking again at how to put more farmland under solar without disrupting operations…

5 November 2026

Data centre probe prompts call for tighter renewable energy requirements in coal state

A NSW parliamentary inquiry has recommended the government require data centres to supply their own…

5 November 2026

Low-cost green hydrogen hopeful lands fresh grant to build pilot at site of proposed offshore wind hub

Green hydrogen CSIRO spin-off wins new grant funding to build fourth pilot plant, this time…

5 November 2026

The rise and fall of the LGC market and the data centre policy decision that will determine its fate

A seemingly niche decision around data centre standards will determine whether LGC prices retain some…

5 November 2026

Huge wind and battery project avoids turbine cuts and name change to win state approval for the West

Developer dodges having to cut 18 turbines from its 750 MW wind plans and change…

5 November 2026

State tightens reins on home energy saver loans after signing up 15,000 households in just 5 months

Energy efficiency is so hot right now. After signing up more than 15,000 households to…

5 November 2026