The Silverton wind farm

Production from the first two turbines of the 200MW Silverton wind farm near Broken Hill has begun, with the project scheduled to be completed by the middle of the year.

So far, 18 of the 58 turbines have been erected for the $450 million project, which has been a major logistical test given its distance from ports and delivery of the major pieces of hardware such as the turbine blades and nacelles.

The first production from the first two turbines was exported to the grid this past weekend, company officials say.

Silverton is the first major greenfield project of the Powering Australian Renewables Fund (PARF), a  partnership between AGL and QIC to own and develop wind and solar projects.

This video will give an idea of the remoteness in the area, some of the issues transporting the major equipment, and erecting the towers and using helicopters to string the transmission wires.

The project is expected to provide  150 jobs at the peak of construction, many of whom worked on the 53MW Broken Hill solar plant, which PARF also operates, and is located about 25kms away.

Silverton was to be the largest wind farm in NSW, but by the time it gets to 200MW it will likely have already been overtaken by the 270MW Sapphire wind farm in northern NSW, which recently started delivering its first 100MW to the ACT government’s 100 per cent renewable program.

Silverton and the 453MW Cooper’s Gap wind farm in Queensland are listed by AGL as part of the response to the closure to the Liddell coal generator in NSW and together are estimated to have a cost of $62/MWh.

The next three stages of the Liddell replacement will include a 300MW solar farm, battery storage, demand management, an upgrade to the Bayswater coal generator, a new 250MW gas plant, and further storage and renewables projects.

The Silverton wind farm is located in the Barrier Ranges about 25kms west of Broken Hill and will feature 58 GE 3.43-130 wind turbines.

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

New Australian developer targets big batteries with four projects in NSW and Victoria

A newly formed Australian renewables and storage developer has unveiled its first four battery projects…

20 March 2025

“Not the right fit:” Community fractured as local council votes to oppose big battery project

Local community is divided over a big battery project in north-east Victoria, and the council…

20 March 2025

“We will not back down:” Court tells Greenpeace to pay billion dollar damages bill to oil and gas company

Billion dollar finding against Greenpeace has implications for green groups in Australia who are also…

20 March 2025

Time for AEMO to get real and stop ringing the alarm bell on gas shortages

AEMO has again downgraded its gas forecasts as consumers choose electrification given the price gouging…

20 March 2025

Iconic fossil fuel smokestacks are being taken down one brick at a time

An old power plant south of Perth is slowly being taken apart, with the chimneys…

20 March 2025

Fewer, bigger turbines proposed as huge green hydrogen project wins first federal head-start funding

Plans to install up to 6GW of wind and solar to produce green ammonia in…

20 March 2025