First turbine goes up at Forrest-backed Clarke Creek wind farm

Published by

The first turbine has been installed at what will be one of the biggest wind farms in Australia, the 450MW Clarke Creek project being built in central Queensland by Andrew Forrest’s Squadron Energy.

The milestone, marking assembly of the first of 100 turbines that will make up the massive project, was shared by Squadron on LinkedIn on Thursday, complete with an “action shot.”

The 450MW project is the first stage of an ambitious multi-gigawatt renewable precinct to be built by Squadron Energy, which recently paid around $4 billion for the renewable developer CWP, which has expertise in building large scale wind and solar projects.

The sign of progress follows a hiccup in the project’s development when tools were downed in May while a change in project managers for was undertaken by Squadron.

As RenewEconomy reported at the time, the project manager being replaced, Windlab, is another company in Forrest’s portfolio. His private interests own 75 per cent of that company, and it was thought that Squadron wanted the contract brought in under a wholly owned company.

The management change also meant a change of construction equipment, which meant all work on the project was put on hold, less than a year after the first sod was turned.

 

Once complete, Clarke Creek will supply around three-quarters of its output to the Queensland government-owned Stanwell Corporation under a 15-year power purchase agreement.

Forrest’s vision for the full Clarke Creek project will include the addition of solar and energy storage capacity – all clustered around a 76,300-hectare site located 150-kilometres north-west of Rockhampton.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Massive carbon capture and storage project pulled from EPBC because of reforms to federal act

EPBC reforms blamed for creating enough uncertainty for global energy giants to withdraw their application…

21 January 2026

Australia’s transition from coal is being held hostage by its obsession with spinning machines

The life extensions to giant coal plants are being driven by fears about grid "security",…

21 January 2026

Solar accounts for three-fifths of US electricity demand growth in 2025, despite Trump’s best efforts

Solar growth also met all of the daytime growth in electricity demand in the US,…

21 January 2026

Remote gold mine sources 88 pct of its power needs in last quarter from wind, solar and battery

One of Australia's biggest gold mines is sourcing nearly 90 per cent of its power…

20 January 2026

SwitchedOn podcast: Why energy companies should be forced to act in their customers’ best interests

Former regulator, Ron Ben-David argues that loyalty penalties, consumer confusion and endless rule-making all stem…

20 January 2026

Gladstone attracts another solar battery hybrid, with $2 billion project that would be Australia’s biggest

A new $2 billion solar and battery hybrid project has entered the federal EPBC queue,…

20 January 2026