First turbine goes up at Australia’s largest wind farm, foundations laid for big battery

Published by

After a sod-turning ceremony in April, TagEnergy says it has started erecting the first of 122 turbines that will make up the first 756MW of the massive Golden Plains wind farm, and the foundations have been laid for its big battery.

In a LinkedIn post and video, TagEnergy updated the construction journey of the project, that will be Australia’s largest wind farm, at 1300MW, once fully complete.

“Golden Plains Wind Farm in Victoria, Australia will be the largest single wind farm in the southern hemisphere when completed,” the post says.

“We reckon a mega-project like this deserves to be documented and celebrated.”

As Victorian energy minister Lily D’Ambrosio says in the video, Golden Plains is expected to deliver about 9% of the state’s energy needs once all 215 of its turbines are up and generating.

The huge project will also feature a big battery, to add flexibility and stability to the grid, for which Tag says it has started laying the concrete foundations.

Golden Plains has been a long time in the development pipeline, most of it under the stewardship of its previous owner, WestWind, before being bought up by TagEnergy just over a year ago.

The project has also been dogged by a series of unsuccessful legal challenges, headed up by the lawyer behind similar battles against fellow Victorian wind project, Bald Hills and against the Delburn wind farm in the Latrobe Valley.

The Victorian government stepped in in June 2022 to amend state planning to allow the wind farm to proceed in the face of the protracted legal challenges. The plaintiffs withdrew all complaints the following month.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

New solar-battery hybrid promising four hours of storage near Canberra seeks federal green light

The local renewable energy arm electronics giant Samsung is seeking a green light from the…

21 July 2026

Who will supply historic gold mining centre’s grid-saving vanadium flow battery?

State government begins evaluating proposals for a 10-hour vanadium flow battery to support the grid…

21 July 2026

“We’re losing time:” Planning delays adding costs and complexity to new renewable projects

Developers say ever increasing planning delays are adding cost and complexity to new wind projects,…

21 July 2026

Solar’s end-of-life problem is not about panel age, it’s about shifting economics and untested plans

Solar decommissioning plans are written into leases and planning consents, but what really determines an…

21 July 2026

The little big battery using local smarts and deeper storage to help fill gap in most renewable grid

Two local companies join forces to help deliver what the world-leading renewables state needs more…

21 July 2026

Scientists identify key material that could finally deliver low cost green hydrogen

Australian and Chinese researchers find that tweaking one key substance could help deliver low cost…

21 July 2026