Failed Australian solar and battery project developer Lyon Solar has been ordered to pay roughly $A6 million plus interest to global PV giant First Solar, after the Federal Court found in favour of the US company.

The judgment, handed down late last week, punctuates a years-long stoush between the two companies, which centred around a loan from First Solar, which had been tapped as preferred PV module supplier in the early stages of several Lyon projects.

In a decision handed down late last week, the Federal Court ruled that the loan agreement with First Solar was valid and that the loan was due and repayable in the sum of $6,016,686.70, with interest.

The Court also found in favour of the plaintiff on the “take-or-pay agreement” claim, finding that the plaintiff was entitled to damages in the amount of $US3.25 million plus interest.

The dispute over the loan had first escalated in late 2017, when the Australian Securities and Investment Commission posted an insolvency notice advising that First Solar had applied to wind up Lyon Infrastructure Investments Pty Ltd.

In November of 2017, First Solar succeeded in obtaining an injunction against Lyon from selling certain assets pending a resolution of the dispute, and also won a federal Court order for ASIC to reinstate the company, which had been de-registered.

At that point in time, Lyon was still claiming to have the largest pipeline of solar and storage projects in Australia – 1700MW of solar and 1000MW of battery storage across South Australia, Victoria, NSW, and Queensland – and to be in the last stage of selling its three most advanced projects.

Two years later, in October 2019, Lyon Infrastructure Investments 1, Lyon Solar and Lyon Battery Storage were placed in the hands of liquidators, Deloitte.

In January of 2020, a report to ASIC by Deloitte painted a bleak picture for the Lyon’s various creditors – which included Japan energy giant Jera and US investment firm Magnetar – who were believed to be owed around $30 million, collectively.

The Deloitte report flagged that the creditors might get no return from the liquidated assets, depending on the sale price of Lyon’s undeveloped projects, and questioned the actions of Lyon directors, including for possibly trading while insolvent.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Concrete foundations completed for all 18 turbines at first and smallest wind farm to begin construction this year

All 18 of the concrete turbine foundations have been poured at the first wind farm…

24 October 2026

Snowy profits steady amid pumped hydro strains, while CEO Barnes sees his take-home benefits sink below $2 million

Snowy Hydro reports a modest uptake in profits in the year to June 2026 while…

23 October 2026

“Reset 3.0” doesn’t answer the biggest questions about Snowy’s $25 billion-plus pumped hydro gamble

Engineering marvel or financial folly? We've been here before - a cost blowout and a…

23 October 2026

Energy Insiders Podcast: Fast lane to electric, and Snowy blowouts

Bruce Hardy from the Energy Futures Foundation on the fast track to electric transport, and…

23 October 2026

Energy efficiency has finally become an election talking point, but for all the wrong reasons

State Liberals and mainstream media are keen to criticise Victoria's popular energy upgrades scheme, but…

23 October 2026

“What’s better, gas or starvation?” Pipeline giant’s extraordinary response to Beetaloo critics

At a contentious annual general meeting, activist shareholders have questioned the viability of future greenfield…

23 October 2026