Wind

First giant turbine finally installed at Victoria’s Mortlake South wind farm

Published by

The first of 35 wind turbines has been completed at Acciona Energy’s 157.5MW Mortlake South wind farm in Victoria’s Western District, putting the project on track to be completed in the first half of 2021.

Spain-based wind giant Acciona said on Friday that the milestone was achieved at the wind farm late last week – a feat of engineering that lifted in place one of the heaviest and highest capacity turbines in Australia, at 4.5MW. (It would have been the biggest, as claimed, were it not for the Bango wind farm in NSW using GE’s Cypress turbines, which have a rated capacity of 5.3MW each.)

The $275 million project is one of six winners of the Victorian government’s renewable energy auction in September of 2018, and appears to have taken a while to reach this new milestone, considering construction works began back in early 2019, according to Acciona.

A spokesperson for Acciona said the long lead time was mostly due to restrictions and delays caused by Covid-19, but that construction was now in full swing and the turbines – the towers for which are being manufactured in Australia, at Hayward’s Steel in Tasmania – were expected to go up at an average rate of one a week between now and late April.

“Building a wind farm is a significant undertaking, and after so much preparation, and particularly in light of the COVID-19 pandemic, we’re pleased to see the towers going up,” said Acciona Energy’ managing director Brett Wickham.

“Our team is working hard, and our local subcontractors continue to contribute their valuable skills to this project – we couldn’t do it without them, and we thank the community for their ongoing support.”

Commissioning will then follow. Mortlake South will connect to the grid via the “state’s first” underground transmission line – a late addition to the project’s design due to strong local objections to the addition of more overhead transmission lines in the area.

Once commissioned, the wind farm will produce 530GWh of renewable energy every year, enough to power up to 117,000 households.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Australia’s top ranked home battery supplier unveils larger all-in-one BESS for commercial and industrial sites

Australia's leading home battery supplier offers bigger all-in-old battery solution for commercial and industrial sites…

27 October 2026

Letting data centres build first, catch up on renewables later could add $40 billion to power bills

Data centres should carry the cost of higher electricity rates if allowed to build now,…

26 October 2026

Well done, Angus: Taylor vows to slash Arena, home battery and EV funding to pay for promised tax cuts

Coalition leader Angus Taylor wants to scrap renewable energy agency, funding for home batteries and…

26 October 2026

Australia enjoys surge in wind, solar and battery projects, with $32.5 billion now financed or under construction

Across Australia, $32.5 billion of generation and storage is now under construction or at financial close,…

26 October 2026

Keep the temperature down: In an anxious world, we need to make the energy transition work for everyone

The response to the shocking attack on Helen Haines suggests we need to bring more…

26 October 2026

The men who fought off Fortescue have a new 4 GW Pilbara wind and solar project in the wings

A new 4 GW wind and solar project is intended to power green iron prospects…

26 October 2026