Final oversize items transported to Granville Harbour Wind Farm

Published by

PRESS RELEASE

Granville Harbour Wind Farm has taken delivery of its final massive wind turbine tower section, marking the end of the project’s 18-week transport program.

In what was the largest transportation program ever seen on the West Coast, a total of 372 oversize items – including tower sections, turbine blades, nacelles, hubs and drive trains – have now been successfully delivered to the remote wind farm construction site, near Zeehan.

Oversize loads were transported using custom-made truck trailers and followed an approved 193-kilometre route starting out from the project’s storage yard, near Bunnings in Burnie.

Oversize loads departed before dawn to minimise disruption to local drivers and were accompanied by experienced Heavy Vehicle Escort Drivers from the Department State Growth.

Project Director, Lyndon Frearson, said news that last deliveries had made it to site safely and without incident had provided the wind farm’s workers with a ‘yet another sense of significant achievement’.

“The transport of our oversize wind turbines has been an incredibly complex undertaking when you consider the nature of North West Coast roads and variable weather conditions,” he said.

“We are indebted to residents and local businesses who have been very patient and understanding of occasional traffic delays that occurred during our oversize transport program.

“Thanks to the collective cooperation of residents, Department State Growth, Councils and emergency services,all loads have now been delivered safely to our construction site”.

Specialist drivers for oversize transport contractor, Rex Andrews, worked a total of 17,820 hours over five months to deliver all items to site.

Transport has continued in recent weeks under current COVID-19 travel restrictions with the wind farm considered an ‘essential’ construction project by the Tasmanian State Government.

Onsite construction works are also continuing in accordance with strictphysical distancing requirements.

A total of 20 wind turbines have now been installed, with the project’s switchyard and 11-kilometre transmission line also complete. 125 specialist workers are currently on the project site.

The wind farm is also in the process of advertising for permanent ongoing technical roles – with up to 5 Tasmanian-based workers required to operate the wind farm once it is complete.

Construction works for the $280 million wind farm are expected to be complete in August this year.

Share
Published by

Recent Posts

Solar Sharer free power offer is being undermined by higher network charges and complex tariffs

Some households will use batteries, EV charging and behaviour change to make very good use…

3 July 2026

China battery giant launches major new push for “circularity” amid EV and home storage boom

China battery giant launches two major initiatives aimed at improving the sustainability of battery manufacturing,…

3 July 2026

Government-backed community battery rollout is way behind schedule, with only a quarter built on time

A report into the progress of the federal government's Arena-backed community battery rollout has revealed…

3 July 2026

One of Australia’s first solar and battery hybrid projects reaches financial close, confirming big shift in market

One of Australia's first solar and battery hybrid projects reaches financial close, confirming big shift…

3 July 2026

Solar battery rebate expanded to apartments and big energy users for up to 30 MWh in game-changing move

State government quietly reboots its paused solar battery rebate and expands the scheme to offer…

3 July 2026

Australian software allows Italian homes to get free power from solar panels in Spain. Why not here?

Innovative energy trading using Australian software is "going gangbusters" in Europe – and making our…

3 July 2026