Final oversize items transported to Granville Harbour Wind Farm

Published by

PRESS RELEASE

Granville Harbour Wind Farm has taken delivery of its final massive wind turbine tower section, marking the end of the project’s 18-week transport program.

In what was the largest transportation program ever seen on the West Coast, a total of 372 oversize items – including tower sections, turbine blades, nacelles, hubs and drive trains – have now been successfully delivered to the remote wind farm construction site, near Zeehan.

Oversize loads were transported using custom-made truck trailers and followed an approved 193-kilometre route starting out from the project’s storage yard, near Bunnings in Burnie.

Oversize loads departed before dawn to minimise disruption to local drivers and were accompanied by experienced Heavy Vehicle Escort Drivers from the Department State Growth.

Project Director, Lyndon Frearson, said news that last deliveries had made it to site safely and without incident had provided the wind farm’s workers with a ‘yet another sense of significant achievement’.

“The transport of our oversize wind turbines has been an incredibly complex undertaking when you consider the nature of North West Coast roads and variable weather conditions,” he said.

“We are indebted to residents and local businesses who have been very patient and understanding of occasional traffic delays that occurred during our oversize transport program.

“Thanks to the collective cooperation of residents, Department State Growth, Councils and emergency services,all loads have now been delivered safely to our construction site”.

Specialist drivers for oversize transport contractor, Rex Andrews, worked a total of 17,820 hours over five months to deliver all items to site.

Transport has continued in recent weeks under current COVID-19 travel restrictions with the wind farm considered an ‘essential’ construction project by the Tasmanian State Government.

Onsite construction works are also continuing in accordance with strictphysical distancing requirements.

A total of 20 wind turbines have now been installed, with the project’s switchyard and 11-kilometre transmission line also complete. 125 specialist workers are currently on the project site.

The wind farm is also in the process of advertising for permanent ongoing technical roles – with up to 5 Tasmanian-based workers required to operate the wind farm once it is complete.

Construction works for the $280 million wind farm are expected to be complete in August this year.

Share
Published by

Recent Posts

Dutton’s nuclear plan a “con job” and a recipe for blackouts, says Bowen

Chris Bowen describes Peter Dutton's nuclear plan as a political "con job", and says while…

19 December 2024

Power, control and symbolic masculinity: How Freud might diagnose the pro nuclear lobby

How would Freud diagnose the pro-nuclear and anti-renewable lobbies? Do not be surprised if it…

19 December 2024

Victoria networks want to be first to own and install EV kerbside chargers on their power poles

A group of local network companies want to be the first to the first to…

19 December 2024

Contested HumeLink transmission line gets federal green tick to connect Snowy 2.0 to the grid

Transgrid’s massive HumeLink transmission line, considered crucial to unlocking capacity of Snowy Hydro 2.0, has…

19 December 2024

US DoE report busts LNG myth, says fossil gas exports are bad for consumers and the planet

US Department of Energy has eroded the fossil fuel industry's arguements for ramping up fossil…

19 December 2024

“Eye glasses for the grid:” New rules pave way for consumer energy to compete with coal and gas

New rule change is progress for Australian consumers seeking to get the most out of…

19 December 2024