It was a long time in the making, but this week Europe’s largest solar PV plant was finally brought online.

The Cestas solar farm, which is 300MW and covers a 250-hectare site near to the French city of Bordeaux, was connected to the grid earlier this month and has already begun producing solar power at a price cheaper than that offered by new nuclear plants.

Developed by Neoen for a cost of €360 million ($382 million), Cestas will see its solar energy for a price of €105/MWh ($111/MWh) for 20 years, which is on a par with wind power and cheaper than the cost of new nuclear energy, confirmed Neoen chief executive, Xavier Barbaro.

France’s older nuclear plants, built in the 1970s and ‘80s, deliver nuclear energy for around €55/MWh, but newer nuclear plants – such as the controversial Hinkley Point development in the U.K., which is being built by French utility EDF – are set to deliver energy for a government-guaranteed price of around €130/MWh.

Barbaro told reporters at the plant’s inauguration that its east-west orientation (solar farms at this latitude are usually oriented with a southern azimuth) means it can produce three-to-four times more power for the same surface area. This also means early morning and late-afternoon production is higher, mirroring more closely typical demand patterns from the French grid.


The plant is comprised of 25, 12MW sub-plants and was delivered to the grid via a consortium of largely France-based contributors, including French infrastructure company Eiffage and Schneider Electric.

At 300 MW, it is easily the continent’s largest single array, and will play its part in pushing France towards 1 GW of new solar PV installations this year, with the country on course to match that in 2016 and 2017, according to projections from Bloomberg New Energy Finance (BNEF).

Share
Published by

Recent Posts

Peter Dutton’s nuclear plan could blow out household electricity bills by up to $600 a year by 2030

New Modelling torpedoes claim that Peter Dutton’s nuclear power plan will be 44% cheaper than…

4 March 2025

The Driven Podcast: The car even beeped at me when I laughed

Fully Charged's Robert Llewellyn on Chinese EVs that make a lot of beeping noises, Elon…

3 March 2025

Pumped hydro doesn’t have to be expensive: If it is, it might be in the wrong spot

Australian pumped hydro project proposals tend not to be located at premium sites, which translates…

3 March 2025

Guarantee of Origin rules for renewable superpower plan hit below the baseline

The Guarantee of Origin or GO rules include a compromise on below-baseline certificates for generation…

3 March 2025

Federal Labor backs “bill busting” energy upgrades for social housing, including home batteries

A new $12.9 million investment from the federal government will support the continued rollout of…

3 March 2025

“More megawatt-hours for the same dollars:” Battery prices coming down as demand soars

The team behind Victoria's first four-hour battery says costs are coming down as technology improves.…

3 March 2025