EPBC gives green tick to massive Queensland battery in just 41 days, now for the state

Published by

Global investment giant Quinbrook has been given the federal green light for its ambitious Queensland big battery plans, less than two months after referring them for environmental assessment under the EPBC Act.

The 780 megawatt (MW), 2,200 megawatt hour (MWh) Supernode North battery and substation just south of Townsville, in Queensland, was this week cleared as “not a controlled action” by the federal environment minister, moving the huge project closer to construction.

Unlike Quinbrook’s first battery in the state, the Supernode South Pine edition in Brisbane which is geared towards supporting an on-site data centre, the northern version will be the backbone of an $8 billion polysilicon factory – Australia’s first. 

The next hurdle for Supernode north will be securing the state government sign-off.  

The local development application, submitted by Quinbrook’s development arm Private Energy Partners, was rejected by the Townsville City Council in December because midway through the process, the state government changed the rules for big batteries.

Big batteries are now impact accessible, and have to put together the same community benefits arrangements that wind and solar projects do. 

All of which means the final sign off now lies with the Queensland government’s State Assessment and Referral Agency (SARA), rather than local councils.

It pays to follow the new rules laid out in December, as two big batteries have been called-in by planning minister and anti-renewables MP Jarrod Bleijie this year and another is waiting to see if it will be as well. 

The latest call-in, a process where a minister intervenes in development applications, was Trina Solar’s Pleystowe battery, which it promptly dumped. 

However, Queensland Conservation Council chief Katie-Anne Mulder believes it would be a brave minister to go against a council’s wishes when it comes to planning – and the Townsville City Council is backing the site where Quinbrook wants to put its new battery.

The council is managing the development of the Lansdown Eco-Industrial Precinct, with proposals for green hydrogen, battery making, and of course the Solquartz polysilicon plant.

Quinbrook is backing the polysilicon plant which will provide feedstock for Australia-made solar panels, which its battery will help to run. 

The Northern Quartz Campus sits north of where the 330  kilovolt (kV) CopperStrong transmission line will hook into an existing 275 kV line heading up to Townsville. 

Already there are three big solar projects within 30km of the new Supernode site being planned, and one already operational. 

If you would like to join more than 28,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Rachel Williamson

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Share
Published by

Recent Posts

One of Australia’s biggest wind farms forced to revisit off-take deals after lengthy construction delays and repairs

The lengthy delays at what would have been the country's biggest wind farm have forced…

3 October 2026

Still in the dark: Snowy Hydro’s awkward anniversary marked without promised review of Snowy 2 costings

The public remains largely in the dark about the full cost of the giant Snowy…

3 October 2026

Energy Insiders: Australia’s diesel dependence is not normal

Amandine Denis-Ryan from IEEFA on what can be done about Australia's unique and unhealthy dependence…

2 October 2026

September was Australia’s second hottest on record, and second driest in the east, BoM data shows

For maximum readings, September came in as Australia's third warmest. For minimums, last month narrowly…

2 October 2026

Chart of the day: Ten years of diesel rebates almost pays for a new truck

Diesel fuel tax credits earned over 10 years nearly equate the price of a huge…

2 October 2026

Biggest wind farm in two years reaches financial close, the ninth in last 12 months, and a new big battery

Updated: The biggest wind farm to reach financial close in Australia in the last two…

2 October 2026