EnergyAustralia downgraded over coal plant breakdowns, coal supply shortages

Published by

The repeated breakdowns at the ageing Yallourn coal generator in Victoria and the coal supply shortages at the Mt Piper coal generator in Victoria have led to a significant downgrade of EnergyAustralia by the international ratings agency S&P Global Ratings.

The downgrade to BBB- from BBB+, and its negative watch, will lead to a bigger bill for borrowings, and comes as analysts take stock of depleted earnings, margin calls, and the possibility that EnergyAustralia – one of the country’s big three “gen-tailers” – may breach its debt covenants and go its parent for more funds.

EnergyAustralia and other big coal generators should be rolling in windfall profits given the high wholesale electricity prices in Australia, but the fact that many have suffered multiple outages and have also had to buy coal supplies on the spot market has led to big losses instead.

S&P says EnergyAustralia is facing a $200 million hit to its earnings this calendar year, a $1 billion liquidity crunch on the margin calls, and its ability to cash in on high prices in coming years is in doubt because its coal generators are not reliable.

“EA has faced several unplanned outages at its coal plants, mainly at the ageing Yallourn plant, along with coal supply shortages at Mount Piper. Management actions have not yet materially improved operational performance over the past few years,” it noted.

“Exacerbating this are volatile wholesale market conditions. Several baseload coal plant outages, extreme weather, low output from renewables, and high demand have forced up electricity prices.”

It says EA faces potential liquidity issues, despite a cash balance of around $490 million, and will have to use its parent company CLP as a “backstop” for any further liquidity needs “over the next 12 months at least.”

The issue is further complicated by the uncertainties created by the age of Yallourn plant, questions about resumption of adequate coal to Mount Piper, and the future course of coal prices.

EA also needs to spend on transitioning its portfolio to replace its retiring fleet, including in at least one big battery project in Victoria, and potentially some pumped hydro projects in NSW.

“We believe EA may be at risk of breaching one of its debt covenants, being the interest coverage ratio. The interest coverage ratio threshold is required to be greater than 1.45x and is calculated on a rolling 12-month basis as of end of June and December.

“We believe that the management will be proactive in managing any potential breaches, if required. We will monitor the progress; and this risk is incorporated into the negative outlook.

S&P notes that EA’s dependence on fossil fuels (54 per cent coal and 30 per cent gas) that are subject to more frequent outages and other operational issues leave it exposed to climate transition risk, like its other big peers who have also failed to keep up with the switch to renewables.

“Exposure to flooding and end-of-life asset retirement costs and associated waste management also increase medium-term environmental risks.”

Meanwhile, Origin Energy, which has made similar profit warnings because of coal supply problems for its Eraring coal generator, has confirmed one of the four units at what is the country’s biggest coal generator remains out of action.

“A fault caused unit 1 at Eraring to come offline on Tuesday evening, and our onsite team is currently working to diagnose the cause and the actions we need to take to rectify it over coming days. Eraring’s other units are not affected,” a spokesperson said.

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and is also the founder of One Step Off The Grid and founder/editor of the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former business and deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

One of Australia’s biggest battery projects seeks green tick for site next to giant Victoria smelter

UK storage developer that has landed a federal government contract to build the biggest battery…

29 September 2024

Energy Insiders Podcast: How to get demand response out of the grid

Carl Hutchinson, the country manager of Enel X, on the difficulties of getting demand response…

27 September 2024

As Victorians prepare to watch the AFL grand final on TV, their rooftop solar may have to be switched off

AEMO issues "minimum load" warning for Victoria as the state heads into the AFL grand…

27 September 2024

New solar cells break efficiency record – and could supercharge how we get energy from the Sun

Recent developments toward high efficiency perovskite-silicon tandem cells indicate a bright future for solar power,…

27 September 2024

Australia’s biggest wind farm proposed to fill gap as last coal generators exit grid

Spanish wind giant is proposing a 3 gigawatt wind project in the south-west corner of…

27 September 2024

Macquarie offshoot to build its first wind farm after $740 million project reaches financial close

Aula Energy, a newly launched offshoot of finance giant Macquarie, is to build its first…

27 September 2024