EnergyAustralia accelerates closure of Mt Piper coal plant ahead of ministers meeting

Published by

EnergyAustralia says it has brought forward the closure of the Mount Piper coal-fired power station in NSW by three years, as part of a plan to accelerate its exit from coal.

EnergyAustralia had originally indicated that the 1,400MW Mount Piper coal power station – near Lithgow – could operate until at least 2043.

But in a new Climate Change Statement published on Thursday, EnergyAustralia says it will now aim to transition entirely out of its coal generation assets by 2040.

This will see the power station close three years earlier than originally planned, and follows a decision by EnergyAustralia to bring forward the closure of the Yallourn power station in Victoria by four years, starting in 2028, after striking a deal with the Victorian government.

“The energy transition has significant impacts for our power station workers and our local communities,” EnergyAustralia managing director Mark Collette said in a statement on Thursday.

“While Mt Piper’s ultimate retirement date will be determined by several factors, we are committed to long term planning and supporting the transition for our workers and our local communities.”

“For our customers we need to ensure that we can maintain reliable, affordable and low emissions energy as the system transitions. This is a real-world challenge that we must meet by employing a range of technologies.”

The new statement details specific emissions reduction targets for EnergyAustralia, including a goal to reach net zero emissions by 2050 and an interim target of reducing its direct carbon dioxide emissions by more than 60 per cent by 2028-29.

Most of the interim target will be achieved through the closure of the brown coal fuelled Yallourn power station, which ranks as one of Australia’s most emissions intensive generators.

EnergyAustralia said that it would also look to invest in low emissions replacement infrastructure, including a 350MW four-hour big battery at the Yallourn site.

“We have, and will continue to make, significant investments as part of our commitment towards reaching net zero emissions. This includes projects such as our carbon neutral gas and hydrogen power plant in New South Wales, Tallawarra B, and the Wooreen battery at Jeeralang in Victoria,” Collette said.

EnergyAustralia has also signed an offtake agreement with the Kidston pumped hydro project, currently being constructed by Genex in Queensland.

“Our approach continues to be one of long-term planning, where we consult with governments and communities as we design and deliver our transition – while ensuring our 2.4 million customers maintain access to reliable and affordable energy,” Collette added.

Pointedly, the announcement comes just a day before federal, state and territory ministers are to meet to discuss proposed reforms to the National Electricity Market, including a controversial ‘capacity market’ proposal that would be designed to prevent the early closure of coal fired power stations.

It is understood that EnergyAustralia has been one of the strongest advocates for a proposed capacity market mechanism – as one of Australia’s largest operators of coal power stations.

The announcement, and its timing, will likely be seen as a means of placing pressure on a number of state and territory energy ministers who have spoken out against a capacity mechanism that is intended to keep coal plants operating for longer.

That mechanism is being opposed by energy ministers from the ACT, New South Wales and Victoria.

NSW energy minister Matt Kean says he favours bilateral talks with companies to manage coal exits, just as Victoria had done over Yallourn.

You can read RenewEconomy’s preview of Friday’s meeting of energy ministers here.

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.
Michael Mazengarb

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.

Share
Published by

Recent Posts

State owned utility’s third big battery officially opened, and is “re-rated” to be the biggest in Australia

State owned Synergy has formally opened its third big battery, which turns out to the…

8 February 2026

Spanish giant completes Sydney battery ahead of schedule, lands contract for a bigger one

Spanish giant completes one big battery project ahead of schedule as it lands a contract…

8 February 2026

Regulators are asking hungry data centres to pay more for grid power, so households can pay less

Some countries now require data centres to pay more to access grid power, but Australian…

8 February 2026

Pumped hydro is vital to the future grid. So why does gas exploration get all the tax benefits?

When gas companies drill a dry hole, the tax system shares the loss; when pumped…

8 February 2026

Home battery numbers shrink for the first time since rebate launch, as installers take a beat

Even the booming home battery market could not escape the January doldrums, with the summer…

6 February 2026

We need more hydro, Turnbull says: But would many smaller projects have been better than Snowy 2.0?

Malcolm Turnbull says more "simpler" pumped hydro needed as solar outpaces wind, and insists that…

6 February 2026