Energy-from-waste facility refused due to ‘uncertain’ health, environment impacts

PRESS RELEASE

The Independent Planning Commission has rejected plans for an energy-from-waste facility in Sydney’s west citing ‘uncertainty’ over human health and environmental impacts.

The Next Generation (NSW) Pty Ltd sought approval to build and operate the large 24/7 facility at Eastern Creek – combusting 552,500 tonnes of the city’s non-recyclable waste every year, generating enough electricity for 100,000 homes.

The state significant development application was referred to the Commission for determination in April after the Department of Planning and Environment received 949 public objections. Blacktown and Penrith City Councils also expressed their opposition.

Chair of the Independent Planning Commission, Professor Mary O’Kane AC, appointed a three-member panel to decide the matter: Ms Robyn Kruk AO (Chair), Mr Peter Duncan AM and Mr Tony Pearson.

The Commissioners met with the applicant and inspected the site and surrounding areas, and spoke with representatives from the Department and both councils.

They also held a public meeting at Rooty Hill to listen to the community’s concerns about the project, which centred on:

  • potential human health impacts;
  • the size and scale of the proposed facility;
  • the suitability of the site, particularly its proximity to residential areas, schools and playing fields
  • potential environmental impacts; and
  • a lack of community consultation.

Having carefully examined all the evidence and taken the community’s views into consideration, the Commission has today decided to refuse consent for the development application.

In summary, the Commission’s Statement of Reasons for Decision dated 19 July found:

  • the applicant’s predicted modelling, was based on data that is not representative of the actual waste streams proposed to be treated at the energy from waste facility;
  • there is insufficient evidence that the pollution control technologies are capable of appropriately managing emissions from the project and would be agnostic to the composition of the project’s waste stream;
  • there is uncertainty in relation to the air quality, and the relationship between air quality impacts and water quality impacts in the locality;
  • as a result, there is uncertainty in relation to the human health risks and site suitability;
  • it is not satisfied that the project is consistent with certain objects of the Environmental Planning and Assessment Act 1979; and
  • the project is not in the public interest.

“The Commission finds that the key issue in its consideration of the project is the uncertainty around the project’s emissions and the results of the applicant’s predicted modelling. Given this uncertainty, the Commission finds that it is unable to determine the project’s impacts on the locality and has persuaded the Commission to adopt a precautionary approach to the consideration and determination of the project’s impacts on air quality and human health,” the Commission stated in its Statement of Reasons.

“The Commission finds that, while there are benefits to the public from the project, there is sufficient uncertainty around the project’s impacts on air quality, water quality and human health that mean that the project is not in the public interest”.

The Commission’s Statement of Reasons for Decision is available here:

https://ipcn.nsw.gov.au/projects/2018/04/eastern-creek-energy-from-waste-facility-ssd-6236

 

Share
Tags: Governments

Recent Posts

Vanadium: The silvery data centre storage metal that you may never have heard of

Vanadium batteries could be the answer to the expanding, energy-hungry artificial intelligence infrastructure sector, with…

9 August 2026

Bowen launches review of emission caps and credits for Australia’s biggest carbon polluters

Policy review will investigate settings for Australia's 2030 and 2035 emissions reduction targets.

7 August 2026

Energy Insiders Podcast: Will data centres make or break wind?

Kane Thornton has moved from the peak renewables body to data centres, now the presumed…

7 August 2026

Climate Active is dead. The funeral will not be certified carbon neutral

Australia's government-run "carbon neutral" certification scheme is being wound up. It is good news for…

7 August 2026

Australia’s first offshore wind auction is “going ahead as planned,” new energy minister confirms

Victoria's newly appointed energy minister says the state will go ahead as planned with Australia's…

7 August 2026

Labor’s data centre gas double-speak leaves the gate open for dodgy offsets

A promise of banning gas while waving through “gas firming” and “gas peaking” with unlimited offsets leaves…

7 August 2026