Note: This article was updated on July 5 due to amendments from the contributing author. Please see details at end of article.
A small but critical development for behind-the-meter batteries and virtual power plants (VPPs) happened in June. Sellers, purchasers and owners wanting their behind-the-meter batteries to participate in FCAS (frequency control) markets need to take note.
FCAS is an important revenue source for batteries and VPPs, making a third to a half of all revenue for batteries and up to 75% for VPPs. VPPs have also proven to be a significant source of contingency reserve.
For example, last year Energy Locals and Tesla’s VPP achieved the milestone of registering 10 MW into all six contingency FCAS markets through the VPP demonstration trials.
These trials were undertaken to assess whether the standards for participation in the Frequency Control Ancillary Service (FCAS) markets – those defined by the Market Ancillary Services Specification or “MASS” – could be relaxed so that distributed energy resources (DER – think batteries, solar, controllable loads) could more easily participate in them.
Many had hoped and even assumed (as we at New Energy Ventures did) that the changes to the MASS to facilitate the VPP demonstration trial would be permanently adopted into the MASS.
On 14 June, the Australian Energy Market Operator (AEMO) released a Draft Report and Determination on whether it would change the MASS and adopt the change. In short, they have chosen not to. It has left many in the industry wondering what was the point of the VPP Demonstration trial.
Based on our work assisting businesses to set up VPPs, we think the decision by AEMO could have significant ramifications.
This will be especially so for VPPs that have been developed on the basis of the VPP demonstration FCAS specification, but also for the existing batteries and VPPs that have been installed through the VPP demonstration trials such as the Tesla Energy Locals VPP.
This article has two parts:
Before we continue – we should say in advance that sorry, this topic and this article is about as “energy nerd” as it gets. I’m going to assume that if you’re reading this article you probably have at least a passing interest and understanding of FCAS markets.
For those not into the details of FCAS, jump to the end of the article for a short refresher. For those in the know, read on…
The MASS or Market Ancillary Services Specification is the technical specification that participants must meet to be able to participate in the FCAS market. They set out:
Through the VPP Demonstration Trials, AEMO was considering whether to relax the specification set out by the MASS in two key ways:
At the nub of it, both these changes would allow for more flexibility around how VPPs can supply FCAS. The change in measurement resolution would, in many cases, allow vendors to use their existing hardware and not require a dedicated meter, thereby saving on costs and complexity of an additional meter.
Furthermore, the change in metering location to allow device level metering would mean that:
Two solutions now exist to provide FCAS in VPPs, we’ll call them for arguments sake:
With AEMO not changing the MASS, solution 2 will no longer be an option. The implications of this are serious for companies deploying VPP technologies.
It rules out not just Tesla’s solution but other solutions in the market for residential VPPs. Tesla has argued that the cost of implementing site level metering could be as high as $15,000 (but there is some contention here as we discuss in Part 2.)’
The “Tesla solution” with main control unit FCAS measurement
Figure 2 – Dedicated battery and inverter FCAS measurement point. Source: VPP Demonstration FCAS SpecificationNot exactly. But AEMO has definitely made it harder for VPPs and DER to participate in the FCAS markets (arguably when they should be making it easier). We don’t think AEMO has got the balance right on their decision.
The issues raised by the various respondents align closely to their technology and existing commercial positions in the market. The review also highlighted the wide gulf of technology capabilities by various VPP providers. As an example:
It may be possible to use embedded network arrangements to still provide device level metering but this is only practical and economic in C&I VPPs.
We strongly recommend that those with an interest in establishing VPPs push for AEMO to accept device level metering. To that end, responding to the current consultation process in the Draft Report and Determination is advised.
The consultation process closes on 6 August. If you would like to get involved, we suggest that you read Part 2.
If there are no changes to the MASS, providers will need to work within the current technical standard to participate in FCAS markets.
Specifically, this means using metering capable of measuring power flow and frequency at 50ms and offering FCAS at a site level only. This will lift the barriers to VPPs and those barriers might be insurmountable for some battery installations.
If AEMO doesn’t budge on their decision, those businesses participating in the VPP Demonstration Project will have until 30 June 2023 to transition to the current MASS standard from the relaxed rules of the VPP Demonstration FCAS specification.
This section looks at the reasons why AEMO chose not to incorporate the VPP Demonstration FCAS specification into the MASS and seeks to provide some solutions to address their concerns.
We agree with some of their justifications, but ultimately don’t think they got the balance right.
The main argument for 1 second metering is that 50 ms sampling of frequency and power flow is prohibitively expensive (but this is contentious – more below) meaning that it is not practical for small-scale DER. Through the trials and the consultation process, AEMO determined:
One second metering can introduce uncertainty of the order of 16% in power measurements (via Reposit Power). Below is one example of how this might happen, based on measurements from a real DER FCAS provider.
In simplified terms, the calculation of Fast FCAS payment is dependent on the average power “response” in the 6 seconds from when the frequency departs from the Normal Operating Frequency Band. Again in simplified terms, the amount of Fast FCAS delivered is a function of the “area under the curve”.
You can clearly see in the chart that 1s resolution metering means a much greater area under the curve, overestimation of energy delivered (or withdrawn) and therefore over compensation for the service delivered.
Figure 1: Comparison of DER FCAS Provider data at measurement resolutions of 50 ms and 1 second. The Right Riemann sum method is used to interpolate the 1s data, consistent with the FCAS Verification Tool. Source: AEMO MASS Draft DeterminationFair enough. Frequency control is one of the more important parts of the energy market for managing power quality and security. If a large proportion of contingency FCAS was coming from “low quality” sources, the error introduced into the power system is understandably undesirable.
If metering costs are as low as Reposit Power asserts they are, then a dedicated meter for FCAS should not be a major barrier to participation. It is concerning that there is not a lot of consensus on the metering costs, but perhaps this review will assist in converging the market.
The argument for device level metering over connection point metering is that you do not have to duplicate metering hardware that already exists in the inverter or control unit of, for example, a battery.
If AEMO were to allow 1 second metering and device level metering, FCAS verification metering could be performed by the inverter or control device. The arguments against device level metering are as follows:
In our view, the justifications for this decision are very weak and should be challenged. Limiting measurement to the connection point will make it more costly (albeit potentially marginally so) where a separate meter is required in addition to metering that is in an inverter or control unit.
In C&I VPPs there will still be the possibility of using the embedded network frameworks to place an on-market child meter on the battery. This arrangement will enable access by the C&I batteries into the FCAS at a device level through the creation of a new connection point. (The ESB is even considering whether to formalise these arrangements with Flexible Trading Relationships).
But it is not practical and economic for residential VPPs to use this arrangement as it financially isolates the battery from the solar, removing the battery’s ability to provide solar storage. Device level metering can and should be considered to enable more flexibility for VPPs to provide their services.
We spell out some remedies for AEMO’s concerns below.
We agree that settlement needs to be done at a connection point level but the issues raised can be dealt with through a series of practical measures to allow for metering at a device level:
Not adopting asset level metering has been made unnecessarily more difficult than it needs to be and limits important innovation in VPPs.
In the context of the National Energy Objective, making it harder for VPPs to participate in the market is not a good outcome for consumers. Specifically:
Note: This article initially stated that commercial and industrial VPPs would be greatly affected by AEMO not adopting the VPP Demonstration FCAS specification into the MASS. On further analysis, New Energy Ventures determined that it will still be possible to do device level metering through the application of the embedded network frameworks and the creation of child metering points on devices intending to participate in the FCAS market. This approach is only practical and economic for C&I VPPs given the nature of the value stack. In general the arguments hold true more generally for VPPs and that AEMO should reconsider its position. The article was updated on July 5.
James Allston is the founder and managing director of New Energy Ventures (NEV), a specialist management consultancy and data-driven services provider that specialises in new energy technology and service models.
NEV provides advice on the commercial, technical and regulatory aspects of virtual power plants and is working with many of Australia’s leading energy companies to develop them.
There are eight Frequency Ancillary Service Markets (FCAS), two for regulation FCAS (used to raise and lower frequency, updating every 4 seconds) and six for contingency FCAS markets (used to raise and lower frequency back to normal limits over time periods of 6 seconds, 60 seconds or 5 minutes). The FCAS markets’ role in the energy market is to keep the frequency within an acceptable range around 50Hz (The Normal Operating Frequency Band is 49.85Hz to 50.15Hz to be precise). The frequency of the market changes due to mismatches in supply and demand. Too much supply (generation) and the frequency goes up, too much demand (load) and the frequency goes down.
The contingency markets are especially interesting. They are capacity markets, meaning participants are paid to sit and wait for a contingency event to happen. By “contingency event” we mean a frequency deviation caused by large disruption to the grid like a transmission line getting knocked out, a coal fired power plant tripping, or a cloud going over the sun. When this happens, providers of FCAS need to very quickly respond and fill the gap between the supply and demand created by the event.
New data shows unemployed people are also turning to rooftop solar to have certainty about…
South Australia flags new mechanism to underwrite gas generators to ensure it has enough back…
Victoria's SEC emerges as buyer of Victoria solar and battery project that was named a…
Spanish energy giant says it received "strong interest" in green bonds issued to help underwrite…
Melbourne-based shared solar pioneer secures $3.8m to drive local manufacturing of its SolShare technology, which…
The federal government has pushed through EPBC approval for a Victoria solar and big battery…