Sunraysia solar farm.
Decmil has become the latest contracting group to be hit by delays in the commissioning of large scale wind and solar projects, after it revealed that the huge 255MW (DC) Sunraysia solar project in NSW has yet to get the green light from the market operator.
Shares in Decmil slumped nearly 10 per cent, losing 8c to 82c, and taking some $20 million off its market capitalisation, after saying it would suffer a $14 million hit to its cash flows because of a dispute with the project owners John Laing and Maoneng over the delay.
The $277 million contract for the Sunraysia project – which has a long term power purchase agreement with AGL – was announced last October and construction at the facility, near Balranald in NSW, began earlier this year.
Decmil says that all plant, equipment and components necessary for the operation of the works are now complete, and delivered on time.
But it says the solar farm has so far failed to obtain R1 registration of the project from the Australian Energy Market Operator. The R1 registration must be submitted at least three months before commissioning and requires detailed data modelling.
“Decmil confirms it is continuing to support Sunraysia Solar with its R1 registration process, including the performance of additional testing and modelling,” the statement said.
But it says that Sunraysia Solar has refused to award to Decmil an extension of time and an associated adjustment to the contracted date for substantial completion. That means it faces delays in progress payments, including the completion milestone payment, until the issue is resolved.
“Notwithstanding this negative cash impact, Decmil retains sufficient cash reserves and working capital facilities,” it said.
The stock market reaction was probably prompted by the experience with RCR Tomlinson, the contracting giant that was ultimately sunk by cost overruns and delays at a number of its contracted solar projects.
Numerous other contractors have been hit by delays and damages claims from developers from lost revenue. The include Downer Group, Tempo Australia and Bouygues.
Other high profile projects have also suffered lengthy delays, with both the Kennedy Energy Hub – featuring a unique combination of wind, solar and battery storage in north Queensland, and the Bungala 2 solar project in South Australia, still not commissioned and running a year behind schedule.
John Laing has taken a $120 million hit to the value of various renewable energy projects as a result of changes and anticipated changes to so-called “marginal loss factors”, or congestion on the grid. It is thought that the write downs include Sunraysia.
John Laing said at the time it had put future investments on hold in Australia. It has been a leader in a consortium of investors that is seeking changes to the way the losses are calculated to provide greater clarity and reflect what is happening on the grid.
Maoneng, which holds a minority 10 per cent, said it did not wish to comment. The company, which has completed several smaller projects in and around the ACT, has also signed a contract with AGL to provide up to 200MW/400MWh of battery storage, with some of it to be located at Sunraysia.
Tougher rules to protect Australia's environment have been welcomed by developers, but conservation groups say…
Karl Braganza, head of research at the BoM, explains El Niño and what it means…
Freshly minted NEM data shows solar-charged batteries discharging at record levels, helping lower wholesale prices…
It is now well established that the combination of new renewables and the huge growth…
Remote First Nations renewable energy projects are a complicated sell to investors, but a new…
Sod turned at first major solar and battery project to connect to new REZ, at…