Solar

Decmil shares slump after problems at huge Sunraysia solar project

Published by

Decmil has become the latest contracting group to be hit by delays in the commissioning of large scale wind and solar projects, after it revealed that the huge 255MW (DC) Sunraysia solar project in NSW has yet to get the green light from the market operator.

Shares in Decmil slumped nearly 10 per cent, losing 8c to 82c, and taking some $20 million off its market capitalisation, after saying it would suffer a $14 million hit to its cash flows because of a dispute with the project owners John Laing and Maoneng over the delay.

The $277 million contract for the Sunraysia project – which has a long term power purchase agreement with AGL – was announced last October and construction at the facility, near Balranald in NSW, began earlier this year.

Decmil says that all plant, equipment and components necessary for the operation of the works are now complete, and delivered on time.

But it says the solar farm has so far failed to obtain R1 registration of the project from the Australian Energy Market Operator. The R1 registration must be submitted at least three months before commissioning and requires detailed data modelling.

“Decmil confirms it is continuing to support Sunraysia Solar with its R1 registration process, including the performance of additional testing and modelling,” the statement said.

But it says that Sunraysia Solar has refused to award to Decmil an extension of time and an associated adjustment to the contracted date for substantial completion. That means it faces delays in progress payments, including the completion milestone payment, until the issue is resolved.

“Notwithstanding this negative cash impact, Decmil retains sufficient cash reserves and working capital facilities,” it said.

The stock market reaction was probably prompted by the experience with RCR Tomlinson, the contracting giant that was ultimately sunk by cost overruns and delays at a number of its contracted solar projects.

Numerous other contractors have been hit by delays and damages claims from developers from lost revenue. The include Downer Group, Tempo Australia and Bouygues.

Other high profile projects have also suffered lengthy delays, with both the Kennedy Energy Hub – featuring a unique combination of wind, solar and battery storage in north Queensland, and the Bungala 2 solar project in South Australia, still not commissioned and running a year behind schedule.

John Laing has taken a $120 million hit to the value of various renewable energy projects as a result of changes and anticipated changes to so-called “marginal loss factors”, or congestion on the grid. It is thought that the write downs include Sunraysia.

John Laing said at the time it had put future investments on hold in Australia. It has been a leader in a consortium of investors that is seeking changes to the way the losses are calculated to provide greater clarity and reflect what is happening on the grid.

Maoneng, which holds a minority 10 per cent, said it did not wish to comment. The company, which has completed several smaller projects in and around the ACT, has also signed a contract with AGL to provide up to 200MW/400MWh of battery storage, with some of it to be located at Sunraysia.

The Sunraysia Solar website says the project was due for completion this month, but makes clear that the plant itself has not been energised or commissioned.

 

 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by
Tags: Governments

Recent Posts

Contract awarded for concrete foundations and early works for ten massive spinning machines

Contracts awarded for concrete foundations and other early works for ten huge spinning machines required…

22 July 2026

Rinehart-backed miner achieves 90 pct renewables in June quarter, may take processing plant off grid

Mine backed by net zero opponent Gina Rinehart achieved 90 per cent renewable share in…

22 July 2026

Network seeks partners on upgrade to nation’s largest isolated grid, to cram in more renewables

State-owned utility seeks expressions of interest for project and contract management partners on its massive…

22 July 2026

Can EVs help get more out of the grid, for less? Two new grant winners hope to show the way

New federal government grant package backs 14 projects to get more renewables on the grid,…

22 July 2026

Government backs “disaster proposal” to power 2 GW hyperscale data centre with fracked Beetaloo gas

NT government has set aside land for the $40 billion gas-powered AI ambitions of ASX-listed…

22 July 2026

Solar and battery to deliver 80 pct of remote off-grid gold mining town’s power supply

Transition of an off-grid gold mining town from diesel to mostly solar and battery to…

22 July 2026