Solar

Decmil shares slump after problems at huge Sunraysia solar project

Published by

Decmil has become the latest contracting group to be hit by delays in the commissioning of large scale wind and solar projects, after it revealed that the huge 255MW (DC) Sunraysia solar project in NSW has yet to get the green light from the market operator.

Shares in Decmil slumped nearly 10 per cent, losing 8c to 82c, and taking some $20 million off its market capitalisation, after saying it would suffer a $14 million hit to its cash flows because of a dispute with the project owners John Laing and Maoneng over the delay.

The $277 million contract for the Sunraysia project – which has a long term power purchase agreement with AGL – was announced last October and construction at the facility, near Balranald in NSW, began earlier this year.

Decmil says that all plant, equipment and components necessary for the operation of the works are now complete, and delivered on time.

But it says the solar farm has so far failed to obtain R1 registration of the project from the Australian Energy Market Operator. The R1 registration must be submitted at least three months before commissioning and requires detailed data modelling.

“Decmil confirms it is continuing to support Sunraysia Solar with its R1 registration process, including the performance of additional testing and modelling,” the statement said.

But it says that Sunraysia Solar has refused to award to Decmil an extension of time and an associated adjustment to the contracted date for substantial completion. That means it faces delays in progress payments, including the completion milestone payment, until the issue is resolved.

“Notwithstanding this negative cash impact, Decmil retains sufficient cash reserves and working capital facilities,” it said.

The stock market reaction was probably prompted by the experience with RCR Tomlinson, the contracting giant that was ultimately sunk by cost overruns and delays at a number of its contracted solar projects.

Numerous other contractors have been hit by delays and damages claims from developers from lost revenue. The include Downer Group, Tempo Australia and Bouygues.

Other high profile projects have also suffered lengthy delays, with both the Kennedy Energy Hub – featuring a unique combination of wind, solar and battery storage in north Queensland, and the Bungala 2 solar project in South Australia, still not commissioned and running a year behind schedule.

John Laing has taken a $120 million hit to the value of various renewable energy projects as a result of changes and anticipated changes to so-called “marginal loss factors”, or congestion on the grid. It is thought that the write downs include Sunraysia.

John Laing said at the time it had put future investments on hold in Australia. It has been a leader in a consortium of investors that is seeking changes to the way the losses are calculated to provide greater clarity and reflect what is happening on the grid.

Maoneng, which holds a minority 10 per cent, said it did not wish to comment. The company, which has completed several smaller projects in and around the ACT, has also signed a contract with AGL to provide up to 200MW/400MWh of battery storage, with some of it to be located at Sunraysia.

The Sunraysia Solar website says the project was due for completion this month, but makes clear that the plant itself has not been energised or commissioned.

 

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024