New data on the connection of new wind, solar and battery projects in Australia’s main grid reveals a bumper month for connection approvals in the month of December, but the grid is still not transitioning quick enough to meet the federal government’s 82 per cent renewables target for 2030.

In fact, generation data suggests that the growth of renewables has stalled in the last four months.

The Australian Energy Market Operator says in the latest update of its connections scorecard that 19 wind, solar and battery project totalling 4.7 gigawatts had their grid connection applications approved in the month of December alone.

That took the total for the 2023/24 financial year to date to 7.5 GW, from a total of 38 projects – more than the 6.8 GW total for the entire 2022/23 financial year.

That acceleration is welcome – it recognises the massive pipeline of renewable and storage projects, and the eagerness to get on to the grid.

Grid connection approvals reflect the projects that have had their generation performance standards approved, but actual connections and commissioning are still trailing well below the scale needed to more than double Australia’s current share of renewables in just six years.

The AEMO data reveals that just one project, the 30 MW Mannum solar farm in South Australia, achieved registration in the month of December. Registration approval means that the project can begin generation, but no projects reached full output, or commissioning in December.

This graph from the AEMO scorecard reveals the sudden surge in approved applications (on the left), and the lack of growth in registrations and full commissioning (centre and right).

Interestingly, this is being reflected on the main grid, where the annualised totals of renewables have changed little in the past few months – stuck at around 38.6 per cent. That is indication of an unwelcome pause, and the delays in actual delivery.

Data from OpenNEM shows that the 12-month rolling average for the month of October was 38.6 per cent renewables, and that is a figure did not change in November or December. At the time of writing, the month of January was heading for the same result – despite numerous “point in time” production records being set over the period.

This next graph from the AEMO connections report highlights another interesting part of the new energy mix and project development mix, and once which is causing concern in some quarters.

Battery projects dominated the list of grid applications in the last fe months, and come second behind large scale solar in terms of pre-registration. Wind energy trails in third place, a concern for some analysts and policy makers because of their importance in balancing out the heavy lean towards daytime solar.

But this trend also reflects the difficulties that wind projects find in the planning process, and also the reality that solar PV module costs are now at or near record lows, even though the “value” of that solar might have diminished due to the number of negative pricing events during the day. But that also provides an incentive for more storage.

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by
Tags: AEMO

Recent Posts

Old king coal risks leaving Australia “in the dark” as aging power plants grow unreliable

New research reveals more than 60% of Australia’s remaining coal power fleet is more than…

23 January 2025

AEMC answers state’s call to use mothballed diesel plants for emergency summer back-up

A temporary energy market rule change will allow two mothballed diesel generators to be used…

23 January 2025

The devil of Frontier’s nuclear modelling is not in the detail, it’s in the omissions

Frontier's nuclear modelling poses a valuable question about the pace of decarbonisation and what we…

23 January 2025

New records for solar and coal underscore urgent energy challenge facing NSW

Australia's biggest coal state continues to reach new solar heights, but a different sort of…

23 January 2025

Transgrid locks in supplier of high-voltage transmission kit for HumeLink project

Transgrid has selected the supplier of more key components of its massive HumeLink project, the…

23 January 2025

Federal green bank gets $2 billion top-up to seize “big opportunities”

As Trump pulls the US out of the clean energy race, the Australian government moves…

23 January 2025