CS Energy to build 50 tonne green hydrogen and refuelling plant in Western Downs

Published by

The Queensland state government is committing $28.9 million towards a renewable hydrogen demonstration plant and refuelling facilities on the Western Downs, in a move the government expects will help to fuel heavy transport in the region.

The Kogan Renewable Hydrogen Demonstration Plant will be built near Chinchilla by as part of a hydrogen refuelling network in the south west of the state being built by the state-owned CS Energy.

The Kogan plant will be located next to the Kogan Creek coal-fired power station, but will only source power from a neighbouring solar plant, along with battery storage, and will produce 50,000 kilograms a year of renewable hydrogen when it comes into operating next year.

“The demonstration plant’s hydrogen electrolyser will only be powered by behind-the-meter solar energy, making it one of the few truly renewable hydrogen projects in Australia,” said Mick de Brenni, Queensland’s minister for energy.

De Brenni said there is strong interest from potential customers in the domestic heavy transport and haulage sector.

“Queensland has a unique competitive advantage in the production of renewable hydrogen, with our proximity to Asia, established infrastructure, manufacturing capabilities and renewable energy generation.

“This project highlights the significant value of Queensland’s publicly owned power stations in the diversification of our state’s future energy portfolio.

The demonstration hydrogen production facility will also include a hydrogen electrolyser, hydrogen fuel cell, hydrogen storage, and out loading facilities.

“This demonstration project will provide CS Energy with valuable expertise and learnings so that we can establish a footprint in the renewable hydrogen sector and prepare for upscaling to commercial scale,” said CS Energy CEO Andrew Bills.

“As Australia’s energy sector transforms, it’s really important that CS Energy diversifies our revenue streams so that we create a sustainable future for the business.”

The construction contract has been awarded to IHI Engineering Australia (a subsidiary of IHI Corporation Japan) and is expected to get underway in September 2022. CS Energy will operate and maintain the plant upon completion, and will form part of CS Energy’s energy hub at Kogan Creek.

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

Vast Energy secures $180m grant for first-of-a-kind solar thermal hub at Port Augusta

Vast's latest ARENA grant will underwrite at least half of what it needs to build…

13 March 2025

Regulatory safety nets not fit for purpose as energy consumers fall victim to rapacious utilities

Energy consumer advocates say proposed electricity price hikes under DMO highlight the need for stronger…

13 March 2025

Rio Tinto signs massive solar and battery deal to help secure future of smelters and refineries

Rio Tinto signs massive solar and battery storage deal to help secure future of its…

13 March 2025

Solar smashes US records with 50 GW added in one year, as Trump’s energy secretary gushes about gas

The US installed record-smashing amounts of solar in 2024 – the largest single year of…

13 March 2025

Huge eight-hour battery project, one of biggest in Australia, locks in supplier

One of the biggest batteries under development in Australia – and one of the first…

13 March 2025

Flicker of hope as LNP allows first of four frozen wind projects to seek planning approval

LNP government allows the first of four giant wind projects that were frozen earlier this…

13 March 2025