Court rejects battery developer bid to be exempt from grid connection fees

Published by

Battery operators will not be exempt from a levy for the construction of the electricity grid if this is required for their connection, one of Germany’s highest courts has ruled.

“Even if they can relieve the overall grid, the installation of battery storage systems does not always benefit the local connection grid for which the construction cost levy is requested,” the Federal Court of Justice said.

Grid operators charge a one-off payment when a grid connection means that power lines need to be constructed or reinforced. This construction levy accounts for a significant portion of investment costs for battery operators, according to a report in energy newsletter Tagesspiegel Background.

The storage industry had hoped for preferential treatment compared to other end consumers, such as households or businesses, because batteries can contribute to grid stability by storing excess electricity and releasing it during shortages.

Storage operator Kyon Energy, which had filed a lawsuit to avoid paying the fee, said that “the consequences of the decision are far-reaching – for investment security in large-scale battery storage, for the planning practices of project developers and for the framework conditions of the energy transition.”

The German Energy Storage Systems Association told pv magazine that the ruling was “a setback for a future-proof energy system and, of course, especially for the storage industry”.

The court agreed that the construction cost levy has a greater impact on battery storage systems than on other end consumers, and that storage systems differ from households and businesses in that they feed electricity back into the grid, acting as both consumers and producers.

However, it concluded that equal treatment of storage systems and other end-consumers was “objectively justified” in accordance with the purpose of the construction levy.

Battery storage systems are a key technology in a renewable energy system, providing flexibility, grid stability, and the ability to bridge periods of low power generation.

However, battery storagesystems are taking up connection capacity, meaning that other grid users waiting to connect – such as industrial companies or data centres – may have to be put on hold.

Clean Energy Wire. Reproduced with permission.

Share
Published by

Recent Posts

Australia’s most powerful battery set free of massive “shock absorber” contract after delay to Eraring coal closure

Australia's most powerful battery now free to trade its full capacity on market after its…

10 October 2026

Look, no turbines! Natural landscape returns at site of decommissioned wind farm

The site of one of Australia's very first wind farms now shows little evidence of…

10 October 2026

Kudos where it’s due: Australia’s quiet role electrifying the rallying cry for the COP we never got to host

The "35 by 35" electrification goal has an Australian origin that the government seems to…

9 October 2026

The Queensland LNP plan for coal-powered data centres could cost taxpayers $20 billion a pop

If we fail to ensure data centres pay for new renewables and storage to cover…

9 October 2026

Home batteries and time-of-use tariffs may be best combination to steer households away from evening peaks

Home batteries look like resetting the behaviour of households when it comes to responding to…

9 October 2026

South Australia won’t reach its 100 pct net renewables target on schedule, but it won’t be the fault of households

South Australia energy minister hints that the 100 pct net renewables target may not be…

9 October 2026