Council says it can’t approve road upgrades in latest attempt to stop contested New England wind project

Published by

A lawsuit trying to stop the contested Hills of Gold wind project in the New England region of NSW is taking a novel attack route by claiming the council can’t legally approve the required road upgrades. 

The Tamworth council was allowed to join the lawsuit in the Land and Environment Court of New South Wales (NSW) against the already state-approved wind farm this week, after losing every other avenue to stop the project from happening.  

Engie’s much reduced Hills of Gold project, proposed for near Nundle in the New England region of NSW, was approved in September in what was seen as a landmark ruling for the industry.

The project has been a lightning rod for opposition, with more than 200 objections to its original 97-turbine design and a similar number against the state planning officials’ approved 47 turbines and 290MW. 

It was only the Independent Planning Commission’s intervention that set the final cap at 62 turbines, totaling 372 megawatts (MW) and with a 100MW battery.

The project received federal environmental approval in March – despite the council begging environment minister Tanya Plibersek to intervene – and is also facing down the court case, which was started by the Hills of Gold Preservation Society.

The Tamworth Regional Council has already lodged six different objections to the wind farm.

Road jurisdiction at heart of suit

The council voted in November to join the suit, with objections ranging from concerns about access roads, land degradation, a lack of social licence, and failures to close deals with landowners who will be affected by the project. 

But its application to join the lawsuit focused on road jurisdiction.

The council says it can’t give planning consent to road upgrades that might encroach on private land, if the landowners haven’t first given their consent, and it doesn’t have enough information yet about public road works.

The council also claims there hasn’t been “substantial” compliance with the secretary’s environmental assessment requirements (SEARs), one of the initial documents that need to be lodged in a planning application. 

It claims Engie is able to comply enough with the SEARS because its environmental impact statement doesn’t contain enough detail around road works – and as a result the council doesn’t have the jurisdiction to give consent.

Senior deputy registrar Donette Holm found that these issues couldn’t be properly dealt with by the court unless the council was part of the claim.

It claimed it would have joined the suit when it was lodged but the council was in caretaker mode ahead of elections.

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Rachel Williamson

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Share
Published by

Recent Posts

One Nation promises to build new coal plants and sweat old ones in energy policy pitch to state voters

One Nation has promised to extend the life of a coal-fired power plant as part…

31 August 2026

Changing tack on Victoria’s energy transition will throw electricity savings into reverse, experts warn

One Nation and Coalition plans to review or roll back Victoria's energy policies would likely…

31 August 2026

“Smart switch:” Retailer tests time-of-use plans in bid to slash bills of hardship customers

State-owned retailer will pilot time-of-use electricity plans across 5,000 select households, to see how much…

31 August 2026

From solar cells to solar farms: Quest for ultra-low cost PV gets $100 million federal boost

Australian Renewable Energy Agency will invest more than $100 million across 20 research and development…

31 August 2026

SwitchedOn podcast: How three hours of free solar power can cost you more

Solar Sharer exposes a fundamental problem with our energy system - protecting retailer revenues can…

31 August 2026

Rooftop solar record tumbles as battery rebate drives 1 GW of new installs over just three months

April to June quarter delivers new records for home batteries and large-scale solar investment, but…

31 August 2026