Transmission

Cost of CopperString transmission line blows out by 20 per cent

Published by

Taxpayers will need to fork out an additional $1.2 billion towards a high-voltage electricity transmission line due to a rise in construction costs and terrain challenges.

The Queensland government has flagged a more than 20 per cent rise in costs for the $5 billion CopperString – one of Australia’s biggest energy grid expansions.

The project will connect Queensland’s northwest to the grid through an 840km power line running from south of Townsville to Mount Isa.

CopperString will be longer than driving from Sydney to Melbourne with the line expected to finish by 2029. 

But now with construction in it’s early stages, Deputy Premier Cameron Dick says the project is not immune to cost increases. 

“That’s why our government has signed off on an additional $1.2 billion in funding to build CopperString if we are re-elected in October,” Mr Dick said on Thursday. 

Queenslanders will head to the polls on October 26. 

The additional funding also does not fall within the state budget handed down by Mr Dick in June.

Difficulties with terrain in one of the “most rugged parts of the world” have also contributed to cost increases, Mr Dick said.

The project had received $11 million in investment decision funding from the former Morrison government in 2020 before the state government purchased private company CuString’s planned CopperString 2.0 project in 2023.

About 200km of additional transmission line is required to connect new renewable generators to to the line, taking it’s total length to over 1000km.

It is set to provide more affordable power to companies mining deposits valued at $500 billion in the North West Minerals Province.

The project will also help unlock the province’s copper, zinc, lead, silver and phosphate needed to make smartphones and renewable energy parts.

Queensland had enshrined into law in April 50 per cent emissions reductions targets by 2030 and 75 per cent by 2035. 

“We’re in a race with the world, not only to extract critical minerals, but also to produce products powered by clean renewable energy,” Mr Dick said.

AAP

Share
Published by

Recent Posts

Breeding grounds, flight paths and climate change: Getting balance right on wind and solar approvals

Environmental approval for wind and solar farms have to consider habitat loss for precious species,…

14 September 2024

Lots of EVs, even more rooftop solar, a gas exodus – and no sun tax: Network sets out 5-year plan

Victoria's biggest electricity network has published its draft five-year plan for the 2026-31 regulatory period.…

13 September 2024

Tesla seeks buyer for Australian virtual power plant, as long as it can supply the batteries and software

Tesla seeks buyer for South Australia virtual power plant, one of the first of its…

13 September 2024

Bon dieu! Hunter Valley solar and battery project seeks approval for site surrounded by coal mines

A solar and battery project proposed for a site surrounded by huge coal mines in…

13 September 2024

Australia inks $660 million hydrogen pact with Germany

A hydrogen investment pact with Germany will support new commercial supply and access to the…

13 September 2024

Labor sets out greener hydrogen strategy, with big new targets and no room for coal

Federal Labor has set out a new plan for Australia to produce at least 15…

13 September 2024